BOYDROCK CONSTRUCTION (40604)
COMPLETED PROJECTS IN 2020
Discover the complete record of infrastructure projects awarded to this contractor, organized by year, region, and implementing agency. Each entry shows detailed contract information including project title, amount, fund source, and completion status — giving a transparent view of performance over time. This data is compiled from the official Department of Public Works and Highways (DPWH) project listings. Source: https://www.dpwh.gov.ph/dpwh/projects/infrastructure (as of 09/25/2025)
Active in the following regions:
Cordillera Administrative Region (27)Back to Contractor Profile- LOCAL INFRASTRUCTURE PROGRAM-REHABILITATION OF ROAD AND DRAINAGE SYSTEM ALONG LAUBACH ROAD, UPPER GENERAL LUNA, BAGUIO CITY< /li>
- Contract effectivity: 2020-10-25
- Contract expiry: 2021-01-06
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱1,472,763.62
- Contract status: Completed Report
- CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOU S INFRASTRUCTURE INCLUDING LOCAL PROJECT-REHABILITATION OF MULTI-PURPOSE HA LL, BAGUIO CITY
- Contract effectivity: 2020-10-25
- Contract expiry: 2020-12-04
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱945,738.12
- Contract status: Completed Report
- CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-QUEZON HILL ROAD # 1 - K0 307+795 - K0 307+907
- Contract effectivity: 2020-07-06
- Contract expiry: 2020-10-26
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱2,974,712.50
- Contract status: Completed Report
- LOCAL INFRASTRUCTURE PROGRAM-REHABILITATION OF BUILDING INCLUDING CONCRETING OF PERIMETER ROAD/WALK-WAY, HEADQUARTERS SUPPORT GROUP , PHILIPPINE MILITARY ACADEMY, FORT DEL PILAR, BAGUIO CITY
- Contract effectivity: 2020-03-13
- Contract expiry: 2021-03-18
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱8,642,471.00
- Contract status: Completed Report
- CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SU PPORT OF NATIONAL SECURITY-CONSTRUCTION OF KILL HOUSE, PHILIPPINE MILITARY ACADEMY, BAGUIO CITY
- Contract effectivity: 2020-02-17
- Contract expiry: 2020-12-02
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱6,639,912.50
- Contract status: Completed Report
- CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF LOC AL ROAD OF SABDANG SHILAN, BALUCAS
- Contract effectivity: 2020-09-21
- Contract expiry: 2020-12-04
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
Data Source:
Department of Public Works and Highways (DPWH) — https://www.dpwh.gov.ph/dpwh/projects/infrastructure
Disclaimer:
The data presented on this page was derived from publicly available information on the official DPWH website. While every effort has been made to ensure accuracy and completeness, discrepancies may occur due to updates or formatting differences. For validation or in case of dispute, please refer to the original source provided above.