GRAM CONSTRUCTION AND SUPPLY (35029)
COMPLETED PROJECTS IN 2023
Discover the complete record of infrastructure projects awarded to this contractor, organized by year, region, and implementing agency. Each entry shows detailed contract information including project title, amount, fund source, and completion status — giving a transparent view of performance over time. This data is compiled from the official Department of Public Works and Highways (DPWH) project listings. Source: https://www.dpwh.gov.ph/dpwh/projects/infrastructure (as of 09/25/2025)
Active in the following regions:
Negros Island Region (42)Region VII (4)Back to Contractor Profile- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, BINOBOHAN,GUIHULNGAN CITY, NEGROS ORIENTAL
- Contract effectivity: 2023-07-07
- Contract expiry: 2024-01-22
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,942,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, PLAGATASANON NATIONAL HIGH SCHOOL, BRGY. PLAGATASANON, GUIHULNGAN CITY, NEGROS ORIENTAL
- Contract effectivity: 2023-07-07
- Contract expiry: 2024-01-22
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,945,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, MAGSAYSAY NATIONAL HIGH SCHOOL, BRGY. MAGSAYSAY, GUIHU LNGAN CITY, NEGROS ORIENTAL
- Contract effectivity: 2023-07-07
- Contract expiry: 2023-11-24
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-EVACUATION CENTERS/ QUARANT INE FACILITIES/ PUBLIC HEALTH FACILITIES-CONSTRUCTION OF BARANGAY HEALTH ST ATION, LAMOGONG, MANJUYOD, NEGROS ORIENTAL
- Contract effectivity: 2023-04-05
- Contract expiry: 2023-08-22
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,943,892.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ER / COVERED COURT, MAGTUHAO, TAYASAN, NEGROS ORIENTAL
- Contract effectivity: 2023-04-05
- Contract expiry: 2023-10-21
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,943,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, HIBAIYO, GUIHULNGAN CITY, NEGROS ORIENTAL
- Contract effectivity: 2023-04-05
- Contract expiry: 2023-08-23
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, IMELDA, GUIHULNGAN CITY, NEGROS ORIENTAL
- Contract effectivity: 2023-04-05
- Contract expiry: 2023-08-23
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, TANGLAD, TAYASAN, NEGROS ORIENTAL
- Contract effectivity: 2023-04-05
- Contract expiry: 2023-08-22
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARA NTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CEN TERS / COVERED COURT, TALAON, LA LIBERTAD, NEGROS ORIENTAL
- Contract effectivity: 2023-03-07
- Contract expiry: 2023-07-25
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES CALAG-CALA G BR. 2 (B00464NR) ALONG DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OC C BDRY), AYUNGON, NEGROS ORIENTAL
- Contract effectivity: 2023-02-07
- Contract expiry: 2023-09-29
- Fund source: Regular Infra - GAA 2023 OO-1
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, BAGTIC, LA LIBERTAD, NEGROS ORIENTAL
- Contract effectivity: 2023-02-07
- Contract expiry: 2023-07-02
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATI ONAL ROAD SYSTEM - BRIDGE PROGRAM - REHABILITATION / MAJOR REPAIR OF PERMAN ENT BRIDGES MALAIBA BR. (B00121NR) ALONG DUMAGUETE NORTH RD. (JCT BAIS-KABA NKALAN-NEGROS OCC BDRY), ALONG DUMAGUETE NORTH RO
- Contract effectivity: 2023-02-07
- Contract expiry: 2023-04-20
- Fund source: Regular Infra - GAA 2023 OO-1
- Contract price: ₱1,960,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, MALABAGO, JIMALALUD, NEGROS ORIENTAL
- Contract effectivity: 2023-02-07
- Contract expiry: 2023-06-26
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS / QUARA NTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CE NTERS / COVERED COURT, SOQUIB, TAYASAN, NEGROS ORIENTAL
- Contract effectivity: 2023-02-06
- Contract expiry: 2023-08-24
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, CAMANDAYON, JIMALALUD, NEGROS ORIENTAL
- Contract effectivity: 2023-02-06
- Contract expiry: 2023-06-25
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARAN TINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENT ERS / COVERED COURT, CABANG, JIMALALUD, NEGROS ORIENTAL
- Contract effectivity: 2023-02-06
- Contract expiry: 2023-06-25
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- CONSTRUCTION OF EVACUATION CENTERS/ COVERED COURT, BAE, JIMALALUD, NEGROS ORIENTAL
- Contract effectivity: 2023-02-06
- Contract expiry: 2023-06-25
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: EVACUAION CENTERS / QUARAN TINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CEN TERS / COVERED COURT, INACBAN, AYUNGON, NEGROS ORIENTAL
- Contract effectivity: 2023-02-06
- Contract expiry: 2023-06-25
- Fund source: Regular Infra - GAA 2023 CSSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALO NG NATIONAL ROADS-TERTIARY ROADS-GUIHULNGAN-BALOC-ISABELA RD - K0117+(-680) -K0117+(-164), K0135+564-K0135+894, K0139+646-K01
- Contract effectivity: 2023-02-03
- Contract expiry: 2023-06-11
- Fund source: Regular Infra - GAA 2023 OO-1
- Contract price: ₱8,908,200.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATI ONAL ROAD SYSTEM - BRIDGE PROGRAM - REHABILITATION / MAJOR REPAIR OF PERMAN ENT BRIDGES ALAWIHAW BR. (B00091NR) ALONG DUMAGUETE NORTH RD. (JCT BAIS-KAB ANKALAN-NEGROS OCC BDRY), MANJUYOD, NEGROS ORIENT
- Contract effectivity: 2023-02-03
- Contract expiry: 2023-04-17
- Fund source: Regular Infra - GAA 2023 OO-1
- Contract price: ₱2,548,000.00
- Contract status: Completed Report
Data Source:
Department of Public Works and Highways (DPWH) — https://www.dpwh.gov.ph/dpwh/projects/infrastructure
Disclaimer:
The data presented on this page was derived from publicly available information on the official DPWH website. While every effort has been made to ensure accuracy and completeness, discrepancies may occur due to updates or formatting differences. For validation or in case of dispute, please refer to the original source provided above.