LECAR BUILDERS (39926)
COMPLETED PROJECTS IN 2019
Discover the complete record of infrastructure projects awarded to this contractor, organized by year, region, and implementing agency. Each entry shows detailed contract information including project title, amount, fund source, and completion status — giving a transparent view of performance over time. This data is compiled from the official Department of Public Works and Highways (DPWH) project listings. Source: https://www.dpwh.gov.ph/dpwh/projects/infrastructure (as of 09/25/2025)
Active in the following regions:
Region X (8)Back to Contractor Profile- CONSTRUCTION OF ROAD ALONG ILIGAN CITY CIRCUMFERENTIAL R OAD (C3) EXTENTION TO JCT. STA. FELOMINA-BUKIDNON-DIGKILAAN-ROGONGON ROAD, ILIGAN CITY
- Contract effectivity: 2019-06-20
- Contract expiry: 2019-10-26
- Fund source: Regular Infra - GAA 2019 LP
- Contract price: ₱27,930,040.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MANDU LOG RIVER, PACKAGE 1, ILIGAN CITY, LANAO DEL NORTE
- Contract effectivity: 2019-06-20
- Contract expiry: 2020-01-29
- Fund source: Regular Infra - GAA 2019 OO-2
- Contract price: ₱18,620,000.00
- Contract status: Completed Report
- WIDENING OF PERMANENT BRIDGES, BANGAAN BRIDGE (B01004MN) ALONG MALABANG-DOBLESTON-TUKURAN ROAD (PHASE II), SND, LANAO DEL NORTE
- Contract effectivity: 2019-07-22
- Contract expiry: 2019-12-28
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱11,750,462.00
- Contract status: Completed Report
Data Source:
Department of Public Works and Highways (DPWH) — https://www.dpwh.gov.ph/dpwh/projects/infrastructure
Disclaimer:
The data presented on this page was derived from publicly available information on the official DPWH website. While every effort has been made to ensure accuracy and completeness, discrepancies may occur due to updates or formatting differences. For validation or in case of dispute, please refer to the original source provided above.