Infrastructure Projects in Cordillera Administrative Region — Cordillera Administrative Region - Cordillera Administrative Region, 2020
This page lists public infrastructure projects implemented by Cordillera Administrative Region - Cordillera Administrative Region in Cordillera Administrative Region during 2020. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| PHESCO, INCORPORATED (145) | 5 | ₱1,016,662,224.00 |
| A.I.P. CONSTRUCTION (32458) / BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION) (8292) | 2 | ₱398,358,624.00 |
| ST. TIMOTHY CONSTRUCTION CORPORATION (39196) | 2 | ₱286,110,016.00 |
| TRYST BUILDERS ENTERPRISES (31164) | 2 | ₱249,697,840.00 |
| BALINTUGAN CONSTRUCTION (34566) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722) | 1 | ₱243,781,200.00 |
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-10-17
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱98,697,936.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECON DARY ROADS BANAUE - MAYOYAO - A. LISTA - ISABELA BDRY ROAD, KO341+(-880) - KO341+(-252), KO341+(-069) - KO348+187
- Contractor: C-BROS CONSTRUCTION (36606) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-08-12
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱116,497,696.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM -ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECOND ARY ROADS NUEVA VIZCAYA - IFUGAO - MT. PROVINCE ROAD, KO291+(-379) - KO291+ 258, KO291+283 - KO295+679, KO295+701 - KO297+6
- Contractor: JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES) (35880)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-05-01
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱101,474,576.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, TALOY NORTE JCT.-SAN PASCUAL BRGY. HALL (SECTION 7)
- Contractor: TRYST BUILDERS ENTERPRISES (31164)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-12-01
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱142,003,840.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B)
- Contractor: BALINTUGAN CONSTRUCTION (34566) / MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. (5733)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-10-03
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱234,199,888.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONST. OF MISSING LINKS/NEW R OADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, ASIN - NANGA LISANJCT. - BAYABAS - MONGLO JCT. (SECTION 1)
- Contractor: OMENGAN CONSTRUCTION & DEVELOPMENT CORPORATION (5119)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-03-15
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱173,494,752.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLISTT
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-12-31
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS /NEW ROADS ABRA CERVANTES ROAD, ABRA
- Contractor: KVC CONSTRUCTION (28959)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-06-20
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱101,325,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TER TIARY ROADS CLAVERIA - CALANASAN - KABUGAO ROADKO703+100 - KO704+260KO704+9 10 - KO706+564
- Contractor: TRYST BUILDERS ENTERPRISES (31164)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-09-15
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱107,694,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TER TIARY ROADS CLAVERIA - CALANASAN - KABUGAO ROADKO699+050 - KO701+393
- Contractor: BHM CONSTRUCTION (30724)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-04-26
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINK S/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A)
- Contractor: A.I.P. CONSTRUCTION (32458) / BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION) (8292)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-09-30
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱235,095,104.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINK S/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL
- Contractor: GOLDRICH CONSTRUCTION & TRADING (16489)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-10-13
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱133,040,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: PROTECT LIVES AND RELIABLE NATI ONAL ROAD SYSTEM - BRIDGE PROGRAM - CONSTRUCTION OF NEW PERMANENT BRIDGES - GAKIAN BRIDGE ALONG GOV. BADO DANGWA NATIONAL ROAD
- Contractor: DJY CONSTRUCTION (35651) / FIAT CONSTRUCTION SERVICES (05463)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-06-20
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY - CON STRUCTION OF APAYAO PROVINCIAL POLICE OFFICE, LUNA, APAYAO
- Contractor: PECDASEN BUILDERS (40316)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-12-23
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱24,125,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY - CON STRUCTION OF POLICE REGIONAL OFFICE CORDILLERA ONE STOP-SHOP NATIONAL SUPPO RT UNIT BUILDING, CAMP BADO DANGWA, LA TRINIDAD,
- Contractor: KUATAKO CONSTRUCTION & GENERAL CONTRACTOR (11224)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-12-27
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱38,694,568.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROAD S KENNON ROADKO235+410 - KO235+480KO235+834
- Contractor: A.I.P. CONSTRUCTION (32458) / BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION) (8292)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-07-27
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱163,263,520.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROADKO228+067 - KO228+170KO229+090 - KO229+2
- Contractor: BALINTUGAN CONSTRUCTION (34566) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-11-18
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱243,781,200.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROAD S KENNON ROADKO237+280 - KO237+391
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-10-12
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱82,210,280.00
- Contract status: Completed Report
- LOCAL PROGRAM -CONSTRUCTION/REPAIR/REHABILITATION/IMPROVE MENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - NATIONAL ROADS AN D BRIDGES - NATIONAL ROADS ABRA - ILOCOS NORTE ROAD, KO431+710 - KO431+920D ANGLAS, ABRA
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-07-20
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱144,725,872.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROV EMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - NATIONAL ROADS A ND BRIDGES - NATIONAL ROADS ABRA - ILOCOS NORTE ROAD, KO434+600 - KO434+870 DANGLAS, ABRA
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-06-20
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱112,953,248.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROV EMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - NATIONAL ROADS A ND BRIDGES - NATIONAL ROADS ABRA - ILOCOS NORTE ROAD, KO446+030 - KO446+080 , KO446+615 - KO446+840DANGLAS, ABRA
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-06-20
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱120,697,376.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROV EMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - NATIONAL ROADS A ND BRIDGES - NATIONAL ROADS ABRA - ILOCOS NORTE ROAD, KO447+540 - KO447+700 , KO448+960 - KO449+100DANGLAS, ABRA
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-06-20
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱107,462,400.00
- Contract status: Completed Report
- LOCAL INFRASTRUCTURE PROGRAM - NATIONAL ROADS AND BRIDGES - NATIONAL ROADS - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLO PE COLLAPSE AND LANDSLIDE ABRA - KALINGA ROAD, KO474+104 - KO474+295LICUAN - BAAY, ABRA
- Contractor: ST. TIMOTHY CONSTRUCTION CORPORATION (39196)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-08-03
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱143,055,008.00
- Contract status: Completed Report
- LOCAL INFRASTRUCTURE PROGRAM - NATIONAL ROADS AND BRIDGES - NATIONAL ROADS - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE AND LANDSLIDE ABRA - KALINGA ROAD, KO453+601- KO453+850LICUAN - BAAY, ABRA
- Contractor: ST. TIMOTHY CONSTRUCTION CORPORATION (39196)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-08-03
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱143,055,008.00
- Contract status: Completed Report
- CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE A ND SEWERAGE / RAIN WATER COLLECTOR SYSTEMS - RAIN WATER COLLECTORS IN PUBLI C FACILITIES - CAR
- Contractor: JOHN-JANN CONST. AND SUPPLIES CORP. (47191)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2020-10-05
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱4,086,775.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES SOO T BRIDGE (B00989LZ) ALONG ABRA - ILOCOS NORTE ROAD
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-12-21
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱530,823,328.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES MARAT BRIDGE (B00989LZ) ALONG JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD ROA D (S005594LZ)
- Contractor: A.I.P. CONSTRUCTION (32458)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-06-16
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱111,336,872.00
- Contract status: Completed Report
- CONSTRUCTION/ REHABILITATION/ IMPROVEMENT OF FACILITIES F OR PERSONS WITH DISABILITIES (PWD) & ELDERLIES/ SENIOR CITIZENS INCLUDI NG GENDER RESPONSIVE FACILITIES
- Contractor: MEP CONSTRUCTION (18759)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2021-12-28
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱28,950,000.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROV EMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL BRIDGES - CONSTRUCTION OF BRIDGE ACROSS TUMBAL RIVER CONNEC TING LUBA TO MANABO, ABRALUBA, ABRA
- Contractor: VIKING CONSTRUCTION & SUPPLIES (18129)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-17
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱28,901,738.00
- Contract status: On-Going Report
- LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONT ROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITIES CONSTRUCTION OF LUBA -SABNANGAN FLOOD CONTROLALONG ABRA RIVER: S
- Contractor: VIKING CONSTRUCTION & SUPPLIES (18129)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-23
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱31,234,988.00
- Contract status: Terminated Report
- LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROAD S AND BRIDGES - LOCAL BRIDGES - CONSTRUCTION OF POBLACION LUBA BRIDGE, LUBA , ABRA
- Contractor: VIKING CONSTRUCTION & SUPPLIES (18129)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱50,445,092.00
- Contract status: Terminated Report