This page lists public infrastructure projects implemented by Cordillera Administrative Region - Cordillera Administrative Region in Cordillera Administrative Region during 2022. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| MG SAMIDAN CONSTRUCTION (33234) | 24 | ₱3,578,108,192.00 |
| PHESCO, INCORPORATED (145) | 14 | ₱3,218,099,512.00 |
| KATHA BUILDERS & SUPPLIES INC. (34651) | 12 | ₱2,021,750,000.00 |
| BALINTUGAN CONSTRUCTION (34566) | 12 | ₱1,720,399,840.00 |
| SILVERWOLVES CONSTRUCTION CORPORATION (48466) | 10 | ₱1,507,288,176.00 |
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUN D - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE A LONG ABATAN - MANKAYAN - CERVANTES ROAD, KO347+
- Contractor: RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-08-04
- Fund source: Regular Infra - GAA 2021 CSSP
- Contract price: ₱96,381,936.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTIO N OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDES - PRIMARY ROADS, KENNON ROADKO234+910 - KO235+020, KO238+870 - KO238
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-11-02
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱173,700,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDES - PRIMARY ROADS, KENNON ROADKO239+297 - KO239+380
- Contractor: A.I.P. CONSTRUCTION (32458) / BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION) (8292)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-08-19
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱91,096,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE OF ROAD:ASPHALT OVERLAY/ITEM 304-A (SLURRY SURFACE TREATMENT 12MM) W ITH CORRECTION - BENGUET - NUEVA VIZCAYA ROAD, K
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-18
- Fund source: Regular Infra - GAA 2021 CSSP
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA AND TUBLAY, KAMOG JCT.-CALOT-PA PPA-BAGONG-BALLUAY-TUEL JCT. (SECTION 2 OF BLIST
- Contractor: KVC CONSTRUCTION (28959)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-06-30
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱77,200,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG LAGAWE RIVER STA 0+000 - STA 0+68
- Contractor: JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES) (35880)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-26
- Fund source: Regular Infra - GAA 2021 OO-2
- Contract price: ₱61,570,860.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES ALONG CONG. ANDRES ACOP COSALAN ROADK0301+(-905) - K030 4+024 (S00386LZ)K0312+000 - K0317+533 (S0038
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-10-03
- Fund source: Regular Infra - GAA 2021 CSSP
- Contract price: ₱144,747,072.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NA TIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENN ON ROAD - K0224 + 985 - K0225 + 090, K0232 + 5
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-01
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NA TIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENN ON ROAD - K0222 + 112 - K0222 + 260TUBA, BEN
- Contractor: A.I.P. CONSTRUCTION (32458) / BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION) (8292)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-01
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NA TIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENN ON ROAD - K0223 + 749 - K0223 + 890TUBA, BEN
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-01
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS CONG . ANDRES ACOP COSALAN ROAD K0318 + 220 - K0318
- Contractor: JOMARCANN GENERAL CONSTRUCTION (30599) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-08-24
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS BENG UET-NUEVA VIZCAYA ROAD K0254 + 270 - K0254 + 3
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-15
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS BENG UET-NUEVA VIZCAYA ROADK0276 + 040 - K0276 + 13
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-11-04
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS BENG UET - NUEVA VIZCAYA ROADKO283+280 - KO283+380,
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-22
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱214,230,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS GOV. BADO DANGWA NATIONAL ROADK0345 + 520 - K0345
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-02-18
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱101,325,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS GOV. BADO DANGWA NATIONAL ROADK0308+979 - KO309+08
- Contractor: DJY CONSTRUCTION (35651) / FIAT CONSTRUCTION SERVICES (05463)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-10
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS GOV. BADO DANGWA NATIONAL ROADK0315 + 721 - K0315
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-18
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱115,800,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS ABAT AN-MANKAYAN-CERVANTES ROAD K0335 + 350 - K0335
- Contractor: RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-03
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱106,081,704.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS MARC OS HI-WAYKO272+800 - KO272+909TUBA, BENGUET
- Contractor: JOMARCANN GENERAL CONSTRUCTION (30599) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-07-19
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱120,625,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS ITOGO N - DALUPIRIP - SN MANUEL BDRY ROADKO275+510 -
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. (5733)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-11-20
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱279,849,984.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS GOV. BADO DANGWA NATIONAL ROADKO288+382 - KO288+53
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-01
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱154,400,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON / UPGRADING OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIAR Y ROADS CITY LIMIT - STO TOMAS ROADKO255+1085
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-24
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS CO NG. ANDRES ACOP COSALAN ROADKO355+100 - KO355+
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-08-05
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱120,625,000.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONT ROL AND DRAINAGE - FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF NAGUEY FLOOD CONTROL, ATOK, BENGUET
- Contractor: 4RMCONSTRUCTION & SUPPLIES (35767) / R.S. SEPIAN CONSTRUCTION & TRUCKING (20519)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-03
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIAB LE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ REC ONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY R OADS GOV. BADO DANGWA NATIONAL ROAD(1) KO348+
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-07-11
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱212,300,000.00
- Contract status: Completed Report
- CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIAB LE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ REC ONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY R OADS (1) BAGUIO - ITOGON ROAD, KO261+370 - KO261
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-10-27
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱212,300,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS CON G. ANDRES ACOP COSALAN ROADKO356+680 - KO356+8
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-02
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱214,230,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS BAGU IO - ITOGON ROADKO260+800 - KO260+954ITOGON,
- Contractor: TRYST BUILDERS ENTERPRISES (31164) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-06-30
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS BAG UIO - BONTOC ROADKO302+180 - KO302+300, KO314+
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-17
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONT ROL AND DRAINAGE - FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF BANEY FLOOD CONTROL AT BARANGAY BACULONGAN SUR
- Contractor: JOMARCANN GENERAL CONSTRUCTION (30599) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-03
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONT ROL AND DRAINAGE - FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF BAGUYOS FLOOD CONTROL AT BARANGAY COLALOMANKAY
- Contractor: RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-09-03
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - SH ILAN - BECKEL ROADKO262+870 - KO263+000, KO263
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-11-21
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - ASSET PRESERVATI ON - PREVENTIVE MAINTENANCE - ASPHALT OVERLAY (INSTAPAVE) ALONG BAGUIO - BO NTOC ROADKO284+969 - KO294+969ATOK, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-02-03
- Fund source: Regular Infra - GAA 2021 CSSP
- Contract price: ₱120,523,720.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - ASSET PRESERVATI ON - PREVENTIVE MAINTENANCE - ASPHALT OVERLAY (INSTAPAVE) ALONG GOV. BADO D ANGWA NATIONAL ROADKO264+050 - KO275+229, KO26
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-09
- Fund source: Regular Infra - GAA 2021 CSSP
- Contract price: ₱120,625,000.00
- Contract status: Completed Report
- CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIAB LE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECO NSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY RO ADS GOV. BADO DANGWA NATIONAL ROAD (1) K0342 +
- Contractor: PHESCO, INCORPORATED (145) / SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-11-02
- Fund source: Regular Infra - GAA 2021 OO-1
- Contract price: ₱492,150,016.00
- Contract status: Completed Report
- LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / I MPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS - ROAD OPENING OF BOLOK - ADAOAY - BAJEN - BATAN ACCESS ROAD, BATAN AND ANCHOKEYKABAYAN, BENGU
- Contractor: DJY CONSTRUCTION (35651) / MXC CONSTRUCTION (46844)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-16
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / I MPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS -FLOOD CONTRO L AND DRAINAGE - FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF A MBURAYAN FLOOD CONTROLKAPANGAN, BENGUET
- Contractor: RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656) / KALAHAN GENERAL CONSTRUCTION AND SUPPLIES (38324)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-08
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,372,296.00
- Contract status: Completed Report
- LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / I MPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONSTRUCTION / IMPROVEMENT OF BEYENG - TACADANG ROAD, TACADANG, KIBUNGAN, BENGUET
- Contractor: DJY CONSTRUCTION (35651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-23
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / I MPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONSTRUCTION / IMPROVEMENT OF DADA - BEYENG - KA YAPA ROAD, DADA, BEYENG AND KAYAPA, BAKUN, BENGU
- Contractor: DJY CONSTRUCTION (35651) / STAY CONSTRUCTION (23323)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-20
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / I MPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL BRIDGES CONSTRUCTION OF CARUMSING BRIDGE, CARUMSING, D ANGTALAN, PASIL, KALINGA
- Contractor: A.I.P. CONSTRUCTION (32458) / ABMJ CONSTRUCTION AND AGGREGATES (43285)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-05-15
- Fund source: Regular Infra - GAA 2021 LP
- Contract price: ₱98,430,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OTCOME 1: ENSURE SAFE & RELIABLE NATI ONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUC TION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS MARCOS HIGHWAY, KO272+800 - KO272+909TUBA, BENGUET
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-01
- Fund source: Regular Infra - GAA 2021 Augmentation
- Contract price: ₱48,250,000.00
- Contract status: Completed Report
- CAPITAL OUTLAY - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/REHABILITATION OF WATER SUPPLY / SEPTAGE & SEWERAGE/RAI N WATER COLLECTOR SYSTEMS - RAIN WATER COLLECTORS IN PUBLIC FACILITIES - CA R, FY 2021
- Contractor: MARYUKAN CONSTRUCTION (45324)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-26
- Fund source: Regular Infra - GAA 2021 CSSP
- Contract price: ₱4,468,252.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTIO N OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROAD, KO241+650 - KO241+790CAMP 7, BAGUIO CI
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-26
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱118,559,904.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, TUEL JCT. - AMBONGDOLAN JCT. (SECTION 3 OF BLISTT OUTER
- Contractor: R.S. SEPIAN CONSTRUCTION & TRUCKING (20519)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-10
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱24,125,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTE NANCE - (ASPHALT OVERLAY) ALONG BAGUIO - BONTOC ROAD, KO312+600 - KO320+600 BUGUIAS, BENGUET
- Contractor: PHILIPPINE CHEMSTEEL INDUSTRIES, INC. (16965)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-02-04
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT . - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-06-16
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT . - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-12
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, LABEY - L ACAMEN PROVINCIAL ROAD (SECTION 4A OF BLISTT O
- Contractor: A.I.P. CONSTRUCTION (32458) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-12
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱164,050,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, LABEY - L ACAMEN PROVINCIAL ROAD (SECTION 4A OF BLISTT O
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-11
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, LABEY - L ACAMEN PROVINCIAL ROAD (SECTION 4A OF BLISTT O
- Contractor: A.I.P. CONSTRUCTION (32458) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-17
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONA L ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/ NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, LABEY - L ACAMEN PROVINCIAL ROAD (SECTION 4B OF BLISTT O
- Contractor: A.I.P. CONSTRUCTION (32458) / BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION) (8292)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-09
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE - (ASPHALT OVERLAY) ALONG BAGUIO - BONTOC ROAD, (S00373LZ) KO294+969 - KO299+760, KO299+820 - KO308+000, (S00375LZ)
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-05-14
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱212,300,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE - (ASPHALT OVERLAY) ALONG BAGUIO - ITOGON ROAD, KO254+(-651) - KO25 8+595, KO261+000 - KO268+055ITOGON, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-30
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱202,650,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECO NDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO301+(-905) - KO304+024, KO313 +175 - KO317+533, KO319+000 - KO322+600, KO324+0
- Contractor: PHESCO, INCORPORATED (145) / UNIMAX STEEL STRUCTURE AND CONSTRUCTION CORP. (49389)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-27
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE ALONG BAGUIO - BONTOC ROAD, KO273+500 - KO281+438ATOK, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-01
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JC T. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT
- Contractor: RANDOM BUILDERS (35258) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-06-03
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS ITOG ON - DALUPIRIP - SAN MANUEL BDRY RD, KO271+216 -
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-06
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / I MPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATA G NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM (TIKAS) - CONST RUCTION OF ENLISTED PERSONNEL 5-STOREY CONDOMINI
- Contractor: SPIDERONE CONSTRUCTION COMPANY LTD. (42805)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-13
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱122,517,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS ITOG ON - DALUPIRIP - SAN MANUEL BDRY RD, KO271+875 -
- Contractor: 3K ROCK ENGINEERING (27908)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-11
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - C ONG. ANDRES ACOP COSALAN RD, KO315+693 - KO315+9
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-11-30
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,650,000.00
- Contract status: Completed Report
- BANAUE - HUNGDUAN - BENGUET BDRY ROAD, KO366+000 - KO366+ 070
- Contractor: DELPAR CONSTRUCTION & SUPPLIES (32677) / BALINTUGAN CONSTRUCTION (34566) / DIMMUBS CONSTRUCTION (48459)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-21
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱57,900,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -TERTIARY ROADS - GOV . BADO DANGWA NATIONAL RD, KO338+038 - KO338+151
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-12
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECO NDARY ROADS - MARCOS HI-WAY, KO260+(-686) - KO264+000, KO264+460 - KO266+00 0, KO266+709 - KO267+165, KO267+325 - KO270+500
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-18
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -TERTIARY ROADS - GOV . BADO DANGWA NATIONAL RD, KO338+753 - KO338+914
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-25
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION / I MPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATA G NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM (TIKAS) - CONST RUCTION OF OFFICE'S 5-STOREY CONDOMINIUM, PHILIP
- Contractor: SPIDERONE CONSTRUCTION COMPANY LTD. (42805)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-08-21
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTI ON OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -TERTIARY ROADS - GOV . BADO DANGWA NATIONAL RD, KO339+323 - KO339+548
- Contractor: BAKUN CONSTRUCTION (29128) / R.S. SEPIAN CONSTRUCTION & TRUCKING (20519)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-25
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,650,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE (ASPHALT OVERLAY) ALONG BAGUIO - BONTOC RD, KO253+(-586) - KO262+00 0LA TRINIDAD, BENGUET
- Contractor: PHILIPPINE CHEMSTEEL INDUSTRIES, INC. (16965)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-03
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱125,450,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL J
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-06-22
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE (ASPHALT OVERLAY) ALONG GOV. BADO DANGWA NATIONAL RD (S00377LZ) KO32 8+(-085) - KO329+420, (S00376LZ) KO320+100 - KO3
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-24
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱212,300,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES ALONG ASIN (KM8) - NANGALISAN - SN PASCUAL, TUBA RD, KO 258+100 - KO268+000, KO269+000 - KO277+780TUBA
- Contractor: PHILIPPINE CHEMSTEEL INDUSTRIES, INC. (16965)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-18
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱77,200,000.00
- Contract status: Completed Report
- BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, A SIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RI NG CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETSABLAN, BENGUET
- Contractor: RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-20
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱173,610,752.00
- Contract status: Completed Report
- BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, GUISSET - BINGA - BALOY - TINONGDAN (SECTION 5 OF BLISTT OUTER RING CIRCUM FERENTIAL ROAD), PACKAGE 1, BENGUETITOGON, BENGUET
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-26
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱231,600,000.00
- Contract status: Completed Report
- CONSTRUCTION OF SAGPAT, KIBUNGAN, BENGUET - SANTOL, LA UN ION ROADSAGPAT, KIBUNGAN
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-21
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱197,860,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUN ITIES - CONSTRUCTION OF PIMINGGAN - SAGUITLANG - LUBAS - DUNGON ROAD IN SUP PORT TO COFFEE, CACAO, BAMBOO, GOLD, LIVESTOCK,
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-22
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱198,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINK S/NEW ROADS - ITOGON - DALUPIRIP - SAN NICOLAS ROADITOGON, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-10
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, ANOVANG DOMOLPOS ITOGON - KAYAPA, N UEVA VIZCAYA, ITOGON BENGUETANOVANG, DOMOLPOS, ITOGON, BENGUET
- Contractor: SEJ CONSTRUCTION & AGGREGATES (36378) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-11
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱297,000,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, KAPANGAN, BENGUET - SAN GABRIEL, LA UNIONKAPANGAN, BENGUET
- Contractor: RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656) / GOLSANG CONSTRUCTION AND DEVELOPMENT OPC (50793)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-11
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱197,943,344.00
- Contract status: Completed Report
- CONSTRUCTION OF SINACBAT - ALILEM ROADBAKUN, BENGUET
- Contractor: BAKUN CONSTRUCTION (29128) / R.S. SEPIAN CONSTRUCTION & TRUCKING (20519)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-19
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱197,895,488.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINK S/NEW ROADS - AGUINALDO - TOBOY - NATONIN ROADAGUINALDO IFUGAO
- Contractor: C-BROS CONSTRUCTION (36606) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-05-04
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱118,212,496.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - TERTIARY ROADS GOV. BADO DAN GWA NATIONAL RD (S00398LZ) KO275+229 - KO276+636, (S00399LZ) KO277+(-367) K O288+980KAPANGAN, BENGUET
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-29
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, K O293+245 - KO293+308BOKOD, BENGUET
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-26
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱115,800,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, K O293+010 - KO293+245BOKOD, BENGUET
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-05-03
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱260,550,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, K O284+450 - KO284+590BOKOD, BENGUET
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-19
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - BENGUET - NUEVA VIZCAYA RD, K O281+(-050) - KO281+155BOKOD, BENGUET
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-19
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱135,100,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO314+845 - KO315+000BOKOD, BENGUET
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-22
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO314+719 - KO314+760, KO314+793 - KO314+845BOKOD, BENGUET
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-22
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱125,450,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO314+430 - KO314+563BOKOD, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-28
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO316+549 - KO316+725BOKOD, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-01
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO316+240 - KO316+365BOKOD, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-17
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱130,275,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO316+100 - KO316+240BOKOD, BENGUET
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-01
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO315+940 - KO316+090BOKOD, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-13
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO341+115 - KO341+255KABAYAN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-01
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE- SECO NDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO343+(-746) - KO353+173, KO353 +227 - KO355+100BUGUIAS, BENGUET
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-02
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- CONSTRUCTION OF BEYENG - TACADANG ROADBAKUN & KIBUNGA N, BENGUET
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-21
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱198,000,000.00
- Contract status: Completed Report
- IMPROVEMENT OF MABACA TO TALOCTOC ROAD IN TANUDAN, KALING A
- Contractor: VUC HIGHLAND DEVELOPERS INC. (FORMERLY: VUC ENGINEERING) (7918)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-15
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱130,275,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO318+570 - KO318+690KABAYAN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / AKSUM CONTRACTING CORPORATION (46919)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-31
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱164,050,000.00
- Contract status: Completed Report
- REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOP E COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO319+190 - KO319+320KABAYAN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-06
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE (ASPHALT OVERLAY) ALONG ITOGON - DALUPIRIP - SAN MANUEL BDRY< /li>
- Contractor: PHILIPPINE CHEMSTEEL INDUSTRIES, INC. (16965)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-01-14
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱86,850,000.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MARIIS CANAL (SA N JOSE SECTION), STA. 3+616 - STA. 4+503
- Contractor: DJY CONSTRUCTION (35651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-21
- Fund source: Regular Infra - GAA 2022 OO-2
- Contract price: ₱65,780,192.00
- Contract status: Completed Report
- A) BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD, K0350 + 650 - K0350 + 760B) BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD, K0353 + 710 - K0353 + 804BANAUE, IFUGAO
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-06-22
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱174,635,872.00
- Contract status: Completed Report
- A) BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD, K0358 + 842 - K0359 + 047B) BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD, K0362 + 080 - K0362 + 140BANAUE, IFUGAO
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-05-10
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱124,485,000.00
- Contract status: Completed Report
- MT PROV - CAGAYAN VIA TABUK - ENRILE RD, K0415 + 481 - K0 415 + 608SADANGA, MT. PROVINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / TADIAN GENERAL CONSTRUCTION (35339)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-12
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- MT PROV - CAGAYAN VIA TABUK - ENRILE RD, K0406+453 - KO40 6+692SADANGA, MT. PROVINCE
- Contractor: PHESCO, INCORPORATED (145) / UNIMAX STEEL STRUCTURE AND CONSTRUCTION CORP. (49389)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-02-13
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- BAGUIO - BONTOC RD, KO375+100 - KO375+130, KO375+935 - KO 376+042SABANGAN, MT. PROVINCE
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-16
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱135,100,000.00
- Contract status: Completed Report
- BAGUIO - BONTOC RD - K0379 + 880 - K0380 + 020, K0380 + 9 17 - K0380 + 986BONTOC, MT. PROVINCE
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-05-20
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱154,400,000.00
- Contract status: Completed Report
- BAGUIO-BONTOC RD - K0369 + 640 - K0369 + 910SABANGAN, MT. PROVINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / UNIVERSAL DE LEON CONSTRUCTION AND AGGREGATES (35079)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-16
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱173,700,000.00
- Contract status: Completed Report
- BAGUIO-BONTOC RD - K0374+120 - K0374+285SABANGAN, MT. PRO VINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / J.L. MALECDAN CONSTRUCTION (48471)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-21
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱145,280,752.00
- Contract status: Completed Report
- JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - K0418 + 000 - K0427 + 535, K0427 + 693 - K0428 + 538, K0428 + 735 - K0429 + 741, K0429 + 798 - K0429 + 855, K0431 + 200 - K0433 + 550, K0436 + 316 - K0438 + 000BARLIG & NATONIN, MT. PROVINCE
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-04
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - K0388 + (-1036) - K0399 + 280, K0399 + 362 - K0399 + 504, K0399 + 546 - K0402 + 3 23BARLIG, MT. PROVINCE
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-11
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - K0438 + 000 - K0444 + 150, K0444 + 220 - K0453 + 800NATONIN, MT. PROVINCE< /li>
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-18
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - K0402 + 323 - K0408 + 741, K0408 + 939 - K0409 + 040, K0409 + 090, - K0410 + 816, K0410 + 942 - K0416 + 126, K0416 + 301 - K0418 + 000BARLIG, MT. PROVINCE
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-02-06
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- MT. PROV - CAGAYAN VIA TABUK - ENRILE RD - KO406+340 - KO 406+445SADANGA, MT. PROVINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-24
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- MT. PROV - CAGAYAN VIA TABUK - ENRILE RD - KO406+746 - KO 406+941SADANGA, MT. PROVINCE
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-02
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- MT. PROV - CAGAYAN VIA TABUK - ENRILE RD - KO404+660 - KO 404+770SADANGA, MT. PROVINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-15
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- MT. PROV - CAGAYAN VIA TABUK - ENRILE RD - KO405+150 - KO 405+345SADANGA, MT. PROVINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / RANDOM BUILDERS (35258)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-02
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱106,150,000.00
- Contract status: Completed Report
- JCT TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD RD - KO406+226 - KO406+401, KO406+431 - KO406+490BARLIG, MT. PROVINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-05
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱191,070,000.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAMUT RIVER , STA.18+300 - STA.18+800 AND STA. 18+985 - STA.19+111 (PIEZA SIDE)LAMUT, I FUGAO
- Contractor: DJY CONSTRUCTION (35651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-13
- Fund source: Regular Infra - GAA 2022 OO-2
- Contract price: ₱38,105,040.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NAYON RIVER , STA.13+904 - STA.13+960 AND STA. 13+970 - STA.14+114 (BIMPAL SIDE)LAMUT, IFUGAO
- Contractor: LBJ CONSTRUCTION (41824)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-22
- Fund source: Regular Infra - GAA 2022 OO-2
- Contract price: ₱12,494,941.00
- Contract status: Completed Report
- (A) CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGAWE RIVER, STA. 0+000 - STA. 1+219 (TUNGNGOD SIDE), LAGAWE, IFUGAO(B) CONSTRUC TION OF BOLIWONG FLOOD CONTROL STRUCTURE, STA. 3+858 - STA. 3+900 AND STA. 4+869 - STA. 5+182, LAGAWE, IFUGAO
- Contractor: DJY CONSTRUCTION (35651)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-11
- Fund source: Regular Infra - GAA 2022 OO-2
- Contract price: ₱111,558,912.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, SOLNOB / BELAO - CEMENTO ROAD, BOKO D, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-09
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, BAYATING - MAKIDOT - DACAAN SADDLE, ATOK, BENGUET
- Contractor: 3K ROCK ENGINEERING (27908) / EAJR DE LEON CONSTRUCTION (47717)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-09
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, GUIOENG - LAWAD - SELAC ROAD, AMLIM AY, BUGUIAS, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-19
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, POBLACION - DALINGAOAN - SINACBAT, BAKUN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-19
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,454,472.00
- Contract status: Completed Report
- CLAVERIA - CALANASAN KABUGAO RD - KO646+450 - KO646+472CA LANASAN, APAYAO
- Contractor: ROAD EDGE TRADING & DEVELOPMENT SERVICES (33140)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-09
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱93,172,680.00
- Contract status: Completed Report
- CLAVERIA - CALANASAN KABUGAO RD - KO646+472 - KO646+507CA LANASAN, APAYAO
- Contractor: ROAD EDGE TRADING & DEVELOPMENT SERVICES (33140)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-24
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱88,760,704.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, TINONGDAN PROPER - CAYUCO - CAWAYAN ROAD, ITOGON, BENGUET
- Contractor: BALINTUGAN CONSTRUCTION (34566)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-09
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,439,936.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, UBANGA - CAYAPAS - BALINTAG - DECAN ROAD, BACULONGAN SUR, BUGUIAS, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-15
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- KIANGAN - TINOC - BUGUIAS RD - KO355+520 - KO355+668TINOC , IFUGAO
- Contractor: DJY CONSTRUCTION (35651) / RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-02
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD RD - KO380+320 - KO380+486BONTOC, MT. PROVINCE
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-16
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱226,775,008.00
- Contract status: Completed Report
- JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD RD - KO380+173 - KO380+320BONTOC, MT. PROVINCE
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-20
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- MT. PROV - CAGAYAN VIA TABUK - ENRILE RD - KO418+580 - KO 418+623, KO418+780 - KO418+898SADANGA, MT. PROVINCE
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-05-03
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- GUINZADAN - CAGUBATAN - BALILI (MANKAYAN) ROAD LEADING TO MOGAO MOUNTAIN AND GAWAAN LAKE, PHASE I, TUBO, MANKAYAN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / SILVERSKY CONSTRUCTION (47884)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-20
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, LIWANG - AKMET - DEK-DEK, MANKAYAN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-20
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, CAMP 1 - TABAAN SUR - TABAAN NORTE - TALOY SUR ROAD TO MARCOS HIGHWAY, TUBA, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / UNIVERSAL DE LEON CONSTRUCTION AND AGGREGATES (35079)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-26
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱212,300,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, POBLACION - SAGPAT - LUBO - MADAYME N, KIBUNGAN, BENGUET
- Contractor: STAY CONSTRUCTION (23323)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-13
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, LAB-ANG - AMPUCAO TO BITNONG - ANS AGAN ROAD, ITOGON & TUBA, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / AKSUM CONTRACTING CORPORATION (46919)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-12-05
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- GOV. BADO DANGWA NATIONAL ROAD - KO319+572 - KO319+736KI BUNGAN, BENGUET
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-09
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱115,800,000.00
- Contract status: Completed Report
- GOV. BADO DANGWA NATIONAL ROAD - KO338+320 - KO338+473BA KUN, BENGUET
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-21
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱144,708,160.00
- Contract status: Completed Report
- GOV. BADO DANGWA NATIONAL ROAD - KO319+310 - KO319+460KI BUNGAN, BENGUET
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-03-09
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱115,800,000.00
- Contract status: Completed Report
- GOV. BADO DANGWA NATIONAL ROAD - KO339+548 - KO339+706BA KUN, BENGUET
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-04-05
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱164,050,000.00
- Contract status: Completed Report
- BAGUIO - BONTOC RD - KO347+520 - KO347+577BAUKO, MT. PRO VINCE
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / EGB CONSTRUCTION CORPORATION (FORMERLY: EGB CONSTRUCTION) (13722)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-26
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- BAGUIO - BONTOC RD - KO347+710 - KO347+1014BONTOC, MT. P ROVINCE
- Contractor: BAKUN CONSTRUCTION (29128) / SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-26
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱241,250,000.00
- Contract status: Completed Report
- JCT TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD RD - KO380+1912 - KO380+2104BONTOC, MT. PROVINCE
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-17
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱185,280,000.00
- Contract status: Completed Report
- JCT TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD RD - KO380+1112 - KO380+1295BONTOC, MT. PROVINCE
- Contractor: SILVERWOLVES CONSTRUCTION CORPORATION (48466)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-10-02
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱168,875,008.00
- Contract status: Completed Report
- BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY , KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT. (SECTION 2 OF B LISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 2, BENGUET
- Contractor: PHESCO, INCORPORATED (145) / UNIMAX STEEL STRUCTURE AND CONSTRUCTION CORP. (49389)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱170,804,992.00
- Contract status: Completed Report
- REHABILITATION/RECONSTRUCTION OF VARIOUS INFRASTRUCTURES DAMAGED BY EARTHQUAKE IN CAR-IMPROVEMENT OF SALIN-BALICANAO-SADSADAN ROAD AS AN ALTERNATE ROUTE OF MT. DATA CLIFF SECTION, HALSEMA HIGHWAY WITH REMOV AL OF SLIDES, MT. PROVINCE
- Contractor: SILVERSKY CONSTRUCTION (47884)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-07-20
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱28,950,000.00
- Contract status: Completed Report
- CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE & ; SEWERAGE/RAIN WATER COLLECTOR SYSTEMS- RAIN WATER COLLECTORS IN PUBLIC FA CILITIES - CAR
- Contractor: BOYDROCK CONSTRUCTION (40604)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2022-12-26
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱3,027,124.25
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE II, LA TRIN IDAD, BENGUET
- Contractor: SPIDERONE CONSTRUCTION COMPANY LTD. (42805) / UNIMAX STEEL STRUCTURE AND CONSTRUCTION CORP. (49389)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-02-26
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱289,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JC T. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT
- Contractor: PHESCO, INCORPORATED (145)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-05-04
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱287,397,440.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUN D - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINT ENANCE (ASPHALT OVERLAY) ALONG GOV. BADO DANGWA NATIONAL RD, (S00399LZ) KO3 08+500 - KO318+167, (S00376LZ) KO319+(-840) - KO
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-24
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱193,000,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS /NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, POBLAC ION JCT. - BATUANG - CARANTES JCT. - BALATOC JCT
- Contractor: MG SAMIDAN CONSTRUCTION (33234) / JABEN GENERAL CONTRACTING & ENG'G SERVICES (34934)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-09-06
- Fund source: Regular Infra - GAA 2022 OO-1
- Contract price: ₱151,504,992.00
- Contract status: On-Going Report
- CONSTRUCTION OF ROAD, GADANG - LANAS - AMPONGET - BAGULIN , GADANG & SAGUBO, KAPANGAN, BENGUET
- Contractor: MG SAMIDAN CONSTRUCTION (33234)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2024-04-18
- Fund source: Regular Infra - GAA 2022 CSSP
- Contract price: ₱144,750,000.00
- Contract status: On-Going Report
- CONSTRUCTION OF DPWH BENGUET FIRST DISTRICT ENGINEERING OFFICE MAIN BUIDING, BENGUETLA TRINIDAD, BENGUET
- Contractor: SPIDERONE CONSTRUCTION COMPANY LTD. (42805)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-08-25
- Fund source: Regular Infra - GAA 2022 LP
- Contract price: ₱114,638,408.00
- Contract status: On-Going Report
- CONSTRUCTION OF DPWH REGIONAL OFFICE CAR OFFICE BUILDING , ENGINEER'S HILL, BAGUIO CITY
- Contractor: MEP CONSTRUCTION (18759) / SPIDERONE CONSTRUCTION COMPANY LTD. (42805)
- Implementing Agency: Cordillera Administrative Region - Cordillera Administrative Region
- Region: Cordillera Administrative Region
- Contract effectivity:
- Contract expiry: 2023-11-28
- Fund source: Regular Infra - GAA 2022 LP
- Contract price: ₱114,083,760.00
- Contract status: On-Going Report