Infrastructure Projects in National Capital Region — National Capital Region - Metro Manila 3rd District Engineering Office, 2024
This page lists public infrastructure projects implemented by National Capital Region - Metro Manila 3rd District Engineering Office in National Capital Region during 2024. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759) | 30 | ₱893,638,100.62 |
| TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302) | 22 | ₱409,933,367.25 |
| IM CONSTRUCTION CORPORATION (20074) | 19 | ₱376,619,250.00 |
| MONOCRETE CONSTRUCTION PHILIPPINES, INC. (37811) | 2 | ₱346,344,080.00 |
| JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748) | 18 | ₱322,829,658.25 |
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG A NNEVILLE ST. (PHASE 2), BARANGAY MAYSAN, VALENZUELA CITY
- Contractor: SONPRO CONSTRUCTION (48592)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,452,028.00
- Contract status: Completed Report
- RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, UGONG BR. (B01768LZ) ALONG GEN.T. DE LEON ST., VALENZUELA CITY
- Contractor: GILTOP CIVIL ENGINEERING CONSTRUCTION (51504)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱7,840,000.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE ALONG SERVICE ROAD, BARANGAY GE N. T. DE LEON, VALENZUELA CITY
- Contractor: ISECURE BUILDER AND CONSTRUCTION SUPPLIES (50933)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱9,446,337.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG A LBERTO ST., (PHASE II), BARANGAY GEN. T DE LEON, VALENZUELA CITY
- Contractor: SONPRO CONSTRUCTION (48592)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱18,925,458.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE (BOX CULVERT) ALONG F. FRANCISC O NLEX SERVICE ROAD, BARANGAY GEN. T. DE LEON, VALENZUELA CITY
- Contractor: GILTOP CIVIL ENGINEERING CONSTRUCTION (51504)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱9,453,522.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE (BOX CULVERT) ALONG GOLD EAGLE NLEX SERVICE ROAD, BARANGAY GEN. T. DE LEON, VALENZUELA CITY
- Contractor: SONPRO CONSTRUCTION (48592)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱9,454,951.00
- Contract status: Completed Report
- CONSTRUCTION OF BOX CULVERT AT DE GUZMAN COMPOUND, BARAN GAY GEN. T. DE LEON, VALENZUELA CITY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱18,892,096.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG J. P. RIZAL ST., CALOOCAN CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱35,678,836.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG 3 RD AVENUE WEST, BARANGAYS 43, 44, 45, 46, 47, AND 48, (PHASE 2), CALOOCAN C ITY
- Contractor: NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,727,294.00
- Contract status: Completed Report
- REHABILITATION OF ORAD INCLUDING DRAINAGE SYSTEM ALONG 2 ND AVENUE WEST, (PHASE 2), CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,728,632.50
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG BA RANGAY 86,87, AND 94, (PHASE 2), CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱37,474,916.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG BA RANGAY 66, 69, AND 70, CALOOCAN CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱46,891,952.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG M AGSAYSAY ST. (PHASE 2), BARANGAY MARULAS, VALENZUELA CITY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,401,542.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG BAGONG NAYON, B ARANGAY BAGBAGUIN, VALENZUELA CITY
- Contractor: GILTOP CIVIL ENGINEERING CONSTRUCTION (51504)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱9,629,462.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS, BARANGAY 166, (PHASE 3), CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,951,832.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS, BARANGAY 166, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,926,860.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS, BARANGAY 176 PHASE 9, CALOOCAN CITY
- Contractor: KING EIGHT BUILDERS AND SUPPLY (37325)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱89,565,040.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (DAY CARE CENTE R), BARANGAY 186, CALOOCAN CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,876,200.50
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS IN BARANGAY 179 (PHASE 2), CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-09
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱84,662,808.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , MIDWAY, BARANGAY 183, CALOOCAN CITY
- Contractor: JOSE CRIS BUILDERS (31042)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,821,255.50
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, PINAGBUKLOD, BAR ANGAY 178, CALOOCAN CITY
- Contractor: JOSE CRIS BUILDERS (31042)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,885,054.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG SAMPAGUITA CREE K, BARANGAY MARULAS, VALENZUELA CITY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱14,401,101.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 8T H STREET, CALOOCAN CITY
- Contractor: J. SIMEON CONSTRUCTION (31867)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-09
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,183,048.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS, BARANGAY 176 PH10, CALOOCAN CITY
- Contractor: WAWAO BUILDERS (46535)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-23
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱89,250,704.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS, BARANGAY 167, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱28,753,954.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG SAMPAGUITA CREE K, BARANGAY 171, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,818,676.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, PHASE 4, PKG 8, BARANGAY 176, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱7,799,930.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, BARANGAY 95, CALOOCAN CITY
- Contractor: CARRY-ON CONSTRUCTION (8014)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,594,489.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS IN BARANGAY 179, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-09
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱84,637,888.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG LIRIO RD. , BRGY. 175, (PHASE 2) CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,448,690.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, G. DE JE SUS ST., BARANGAY 146, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,751,080.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS, BARANGAY 174, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱28,873,494.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG L IBIS ESPINA STREET, BARANGAYS 13, 14, AND 16, (PHASE 2), CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,803,523.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG BAR ANGAY 63, (PHASE 2), CALOOCAN CITY
- Contractor: MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,602,299.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE ALONG D. AQUIN O ST., BARANGAY 53, 54, 55, 57, 60, 61 AND 62, CALOOCAN CITY
- Contractor: CARRY-ON CONSTRUCTION (8014)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,219,980.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, BARANGAY 75, CALOOCAN CITY
- Contractor: MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,433,729.00
- Contract status: Completed Report
- REHABILITATION OF FLOOD CONTROL WALL ALONG GEN. T. DE LE ON-PARADA CREEK, BARANGAY GEN. T. DE LEON, VALENZUELA CITY
- Contractor: GILTOP CIVIL ENGINEERING CONSTRUCTION (51504)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱14,386,265.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHA SE 6), VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-08
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,080,792.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHA SE 7), VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-08
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,089,632.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHA SE 8), VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-08
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,079,104.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE SYSTEM, SERVICE ROAD, RAMELON S T., DOCE ST., BARANGAY 156, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,874,471.50
- Contract status: Completed Report
- IMPROVEMENT OF ROAD INCLUDING DRAINAGE SYSTEM, BARANGAY 157, CALOOCAN CITY
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,860,551.00
- Contract status: Completed Report
- REHABILITATION OF DRAINAGE SYSTEM, BARANGAY 158, CALOOCA N CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-05-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,875,644.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, MILAGROS A ST., BARANGAY 150, 152 AND 153, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,748,768.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY 180, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,843,988.50
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS ALONG MATARIK, BARANGAY 175 (PHASE 2), CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759) / ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱85,027,888.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG B ARANGAY 123 & 124, (PHASE 2), CALOOCAN CITY
- Contractor: CARRY-ON CONSTRUCTION (8014)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,976,573.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG B ARANGAY 28, (PHASE 2), CALOOCAN CITY
- Contractor: CARRY-ON CONSTRUCTION (8014)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,595,601.00
- Contract status: Completed Report
- REHABILITATION OF DRAINAGE SYSTEM, TIRAD PASS, BARANGAY 136, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-05-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,869,449.00
- Contract status: Completed Report
- CONSTRUCTION OF BOX CULVERT ALONG BARANGAY 173, CALOOCAN CITY
- Contractor: WAWAO BUILDERS (46535)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-08
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,970,672.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG T ILAPIA STREET, BARANGAY 22, (PHASE 2), CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,803,416.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM, BARANG AY 22, 23, 24, 26 AND 27, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,422,098.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLDING DRAINAGE SYSTEM, BARANGAY 38, 41 AND 42, CALOOCAN CITY
- Contractor: GMO CONSTRUCTION (43912)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,696,745.00
- Contract status: Completed Report
- CONSTRUCTION OF RELIEF PUMPING STATION, BARANGAY MAYSAN, VALENZUELA CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-08-19
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱38,367,628.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CR EEKS ALONG PALMERA, BARANGAY 175 (PHASE 3), CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,975,932.00
- Contract status: Completed Report
- CONSTRUCTION OF BOX CULVERT ALONG 8TH AVENUE EAST, BARAN GAY 101, 102, 103, 104, 105, 106, 107, 108 AND 109, CALOOCAN CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱33,809,064.00
- Contract status: Completed Report
- CONSTRUCTION OF ROADS AND DRAINAGE ALONG MALVAR ST., BRG Y. 178, CALOOCAN CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-05-26
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,623,263.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM, BARANG AY 14, (PHASE 2), CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-04-26
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,801,954.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , TALA ESTATE, BARANGAY 186, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,833,191.50
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG K IPAPA ROAD CONNECTING DEPARO CAMARIN, PHASE 2, BARANGAY 178, CALOOCAN CITY< /span>
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱15,368,295.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG C- 3 ROAD (5TH ST. - TAGAYTAY ST.), CALOOCAN CITY
- Contractor: DREAMWORX BUILDER & TRADING, INC. (34004)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-23
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱19,169,148.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG C- 3 ROAD (DAGAT-DAGATAN AVENUE - PNR), CALOOCAN CITY
- Contractor: J. SIMEON CONSTRUCTION (31867) / MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱38,259,728.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG C- 3 ROAD (CALOOCAN/NAVOTAS BOUNDARY - DAGAT-DAGATAN AVENUE), CALOOCAN CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱38,296,976.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHA SE 9), VALENZUELA CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-05-09
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,086,376.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHA SE 11), VALENZUELA CITY
- Contractor: J. SIMEON CONSTRUCTION (31867) / MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-07-20
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,081,472.00
- Contract status: Completed Report
- CONSTRUCTION OF BRIDGE ALONG MACARTHUR HIGHWAY, BRGY. DA LANDANAN, VALENZUELA CITY
- Contractor: DSA PRIME BUILDERS CORPORATION (51697)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,546,145.00
- Contract status: Completed Report
- CONSTRUCTION OF CONCEPCION MULTI-PURPOSE BUILDING (COVER ED COURT) PHASE 2, BARANGAY MARULAS, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱7,793,288.00
- Contract status: Completed Report
- OFF-CARRIAGEWAY IMPROVMENT - SECONDARY ROADS MINDANAO AV E K0019 + (-309) - K0019 + 898, (S05631LZ) CHAINAGE 0 - CHAINAGE 598, (S056 32LZ) CHAINAGE 0 - CHAINAGE 497
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-05-11
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱44,280,340.00
- Contract status: Completed Report
- REHABILITATION OF DRAINAGE SYSTEM, PANGAKO ST., BARANGAY 151, CALOOCAN CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱7,801,092.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG MAGNOLIA ROAD, B RGY. 174 (PHASE 3), CALOOCAN CITY
- Contractor: KING EIGHT BUILDERS AND SUPPLY (37325)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,219,820.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG SAN ANTON IO (PHASE 2), BRGY. 174, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,641,754.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG PETUNIA ( PHASE 2), BRGY. 174, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,632,341.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG PETUNIA R D. (PHASE 3), BRGY. 175, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,632,341.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG WALING-WA LING EXT. RD., BRGY. 174, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,641,683.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG SUNFLOWER RD. (PHASE 2), BRGY. 174, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,643,891.00
- Contract status: Completed Report
- REHABILITATION OF ROAD AND DRAINAGE AT DEPARO SUBDIVISIO N, BRGY. 168, CALOOCAN CITY
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,878,795.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG SARANAY R D., BRGY. 171 (PHASE 3), CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,246,868.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 4 PKG 8, BRGY. 176, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,876,621.00
- Contract status: Completed Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG UGONG, (SERVICE ROAD NLEX SEGMENT 8. 1 FELICIANO ROAD-QUE BALAG ROAD) VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱13,500,209.00
- Contract status: Completed Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG KARUHA TAN TO MALINTA (FRANCISCO ROAD PAXTON-PINALAGAD), VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱18,297,992.00
- Contract status: Completed Report
- IMPROVEMENT OF ROAD AND DRAINAGE SYSTEM ALONG CAIMITO RO AD, BRGY. 79, CONNECTING TO SAMSON ROAD & MACARTHUR HIGHWAY (PHASE 2), CALOOCAN CITY
- Contractor: KING EIGHT BUILDERS AND SUPPLY (37325)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱24,055,320.00
- Contract status: Completed Report
- REHABILITATION OF ROAD AND DRAINAGE SYSTEM ALONG FLORESC O ROAD, BRGY. 78, CONNECTING TO MACARTHUR HIGHWAY, CALOOCAN CITY
- Contractor: D.C. SANDIL CONSTRUCTION AND REALTY DEVELOPMENT, I (32562)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,651,945.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG B ARANGAY 73, CALOOCAN CITY
- Contractor: MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,709,304.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG S T. FRANCIS ST., BARANGAY 186, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,711,507.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 174, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,805,024.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), STA. QUITERIA VILLAGE, BRGY. 162, CALOOCAN CITY
- Contractor: WAWAO BUILDERS (46535)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,809,975.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG JASMINE R D. (PHASE 2), BRGY. 175, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,399,362.00
- Contract status: Completed Report
- REHABILITATION OF ROAD AND DRAINAGE ALONG 1ST AND PARAIS O ST. BRGY. 175, CALOOCAN CITY
- Contractor: D.C. SANDIL CONSTRUCTION AND REALTY DEVELOPMENT, I (32562)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱23,982,874.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG SANGGUMAY RD., BRGY. 175, CALOOCAN CITY
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,622,148.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM, ALONG BONGANGB ILLA RD. (PHASE 2), BRGY. 175, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,401,677.00
- Contract status: Completed Report
- RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES ALAT BR . (B01749LZ) ALONG NOVALICHES-SN JOSE RD
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱19,161,308.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE - TERTIARY ROADS GEN. T. DE LEON ST - K0013 + 345 - K0014 + 000
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱6,894,259.50
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - TERTIARY ROADS GEN T DE LEON ST - K0013 + (-202) - K0013 + 000, K0013 + (-366) - K0013 + (-202), K0013 + 000 - K0013 + 345
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-06
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱12,917,899.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE FROM PABAYA ST. TO KKK , BRGY. MAPULANG LUPA & BRGY. UGONG, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,507,483.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG FAMILY COMPOUND , BARANGAY KARUHATAN, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱23,912,100.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG CANUMAY WEST CR EEK, BARANGAY CANUMAY WEST, VALENZUELA CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-06
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱43,185,372.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG S T. PAUL ST., BARANGAY 186, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,604,739.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) SMMI, BARANGAY 178, CALOOCAN CITY
- Contractor: A.L. LUCERO CONSTRUCTION SERVICES (48004)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,753,044.00
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - TERTIARY ROADS, CENTRAL LUZON LEP. RD - K0028 + (-895) - K0030 + 284, K0031 + (-698) - K0031 + 724
- Contractor: MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS (17701)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-06
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱94,665,472.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE, MALARIA ROAD TO VICTO RIA WAVE SPECIAL ECONOMIC ZONE, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-05
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱48,093,160.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM, ALONG DEL MUND O RD., BRGY. 167 (PHASE 2), CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,419,369.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE AT GREENVILLE, BRGY. 1 71, CALOOCAN CITY
- Contractor: C.L. MORALES CONSTRUCTION AND TRADING (38367)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,422,707.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG JAGUAR RD . (PHASE 2), BRGY. 175, CALOOCAN CITY
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,622,450.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG BRGY. 168 , CELIA RD. (PHASE 2), CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,223,510.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG SUCABAN R D., BRGY. 166, C ALOOCAN CITY
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,226,166.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE, ROAD LEADING TO CAYBI GA HIGHSCHOOL, BRGY. 165, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,213,882.00
- Contract status: Completed Report
- REHABILITATION OF ROAD AND DRAINAGE ALONG NDR WEST SERVI CE ROAD, BRGYS. 141, 154, 155, 160, 161 CALOOCAN CITY
- Contractor: WAWAO BUILDERS (46535)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱28,780,852.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) A T MELPITAS, PHASE 8A KG4, BRGY. 176, CALOOCAN CITY
- Contractor: C.L. MORALES CONSTRUCTION AND TRADING (38367)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,825,334.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, NATIVIDAD, BARAN GAY 168, CALOOCAN CITY
- Contractor: MK ZACK BUILDERS CORP. (42193)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,815,560.50
- Contract status: Completed Report
- CONSTRUCTION OF ROADS AND DRAINAGE ALONG ROSAL ST., BRGY . 187, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱5,779,859.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG S T.LUKE ST., BARANGAY 186, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,732,937.00
- Contract status: Completed Report
- REHABILITATION OF ROADS AND DRAINAGE ALONG CARMELITE VIL LAGE, BRGY. 187, CALOOCAN CITY
- Contractor: DSA PRIME BUILDERS CORPORATION (51697)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,743,274.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG BARANGAY 183, CA LOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,207,484.00
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - TERITARY ROADS, SAN JOSE - NOVALICHES RD - K0025 + (-692) - K002 8 + 945
- Contractor: MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS (17701)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-06
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱94,568,048.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE SYSTEM ALONG TAGAYTAY STREET, B ARANGAY 126, 127, 128, 129 AND 130, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,410,918.00
- Contract status: Completed Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 10 TH AVENUE (11TH ST. - KAMANTIGUE ST.), CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱19,191,244.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , HORACIO DELA COSTA HOMES II, BRGY. 179, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,864,248.50
- Contract status: Completed Report
- CONSTRUCTION OF ROADS AND DRAINAGE ALONG MT. BALOY ST., BRGY. 183, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,445,218.00
- Contract status: Completed Report
- IMPROVEMENT OF ROADS INCLUDING DRAINAGE LEADING TO GSIS RECREATIONAL PARK, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-06
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱47,970,320.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 174, CA LOOCAN CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,825,300.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE, TEOFILO SAMSON AVENUE TO NORTHSTAR INDUSTRIAL MANUFACTURING/ OTHER MANUFACTURING SITES, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-08
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱47,940,228.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE AT MAHABANG PARANG (LO OBAN), BRGY. BIGNAY, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱22,087,306.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG GEN. TIRONA COR. MALOLOS AVENUE, BRGY. 146, CALOOCAN CITY
- Contractor: MARCO STRUCTURES, INC (36006)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,714,697.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, BARANGAY 172, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,628,391.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG BARANGAY 179, CA LOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱28,664,686.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, MGM ST. GOING TO SITIO GITNA, BARA NGAY 166, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱29,134,566.00
- Contract status: Completed Report
- REHABILITATION OF ROAD AND DRAINAGE SYSTEM ALONG TANDANG SORA EXTENSION ROAD (TULLAHAN ROAD) CONNECTING TO QUIRINO HIGHWAY (PHASE 3 ), CALOOCAN CITY
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,235,716.00
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG S ITIO 6, PHASE 4, DAGATDAGATAN, BARANGAY 178, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,603,384.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT CASIMIRO TOWNHOMES, DEPARO, BRGY. 168, CALOOCAN CITY
- Contractor: MK ZACK BUILDERS CORP. (42193)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,920,885.25
- Contract status: Completed Report
- REHABILITATION OF ROADS AND DRAINAGE SYSTEM ALONG BARANG AYS 16, 18, 20 AND 22, CALOOCAN CITY
- Contractor: SAMJS CONSTRUCTION SERVICES (50737)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱29,149,912.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), AT PROGRESSIVE VILLAGE 2, BRGY. 171, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,821,142.50
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE SYSTEM ALONG BARANGAY 123, CALO OCAN CITY
- Contractor: AIC CONSTRUCTION SERVICES (53710)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,623,075.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 0+000 - ST A. 0+200, BARANGAY 178, CALOOCAN CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱47,851,160.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 173, CA LOOCAN CITY
- Contractor: MK ZACK BUILDERS CORP. (42193)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,816,251.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE SYSTEM, UNION WORKERS, BARANGAY 167, CALOOCAN CITY
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,625,480.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG PITONG BA HAY RD., BRGY. 177 (PHASE 2), CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,427,435.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE AT DEL REY VILLE I, BR Y. 163, CALOOCAN CITY
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱5,788,625.00
- Contract status: Completed Report
- CONSTRUCTION OF ROADS AND DRAINAGE ALONG BO. CONCEPCION, BRGY. 188, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,223,466.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM, ALONG MAYVILLE RD. (PHASE 2), BRGY. 167, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,602,465.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING WITH COVERED COUR T, NORTH TRIANGLE SUBDIVISION, BARANGAY CAMARIN, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,605,190.00
- Contract status: Completed Report
- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, M.B. ASISTIO ST . - DR. UYGUANCO ST., BARANGAY 187, CALOOCAN CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱28,800,370.00
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - SECONDARY ROADS, GEN SAN MIGUEL ST - K0011 + (-732) - K0011 + (- 556)
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-23
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱13,894,184.00
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY A ND REGULATORY SIGNS AND PAVEMENT MARKING-CENTERLINES, EDGE LINES INCLUDING PROFILE EDGE LINES ALONG GEN. T. DE LEON ST. - K0015 + 076 - K0016 + 142, H EN. T. DE LEON, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,555,464.62
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE, PAVEMENT MARKINGS, ZEBRA PEDESTRIAN CROSSING, AND IMPROVE SIGHT DISTANCE-CLEAR OBSTRUCTION AL ONG POLO-NOVALICHES ROAD - K0014 + 868 - K0016 + 100, MAYSAN, VALENZUELA CI TY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱3,616,045.75
- Contract status: Completed Report
- CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING AT M CU, PHASE 8 PKG 4, BRGY. 176, CALOOCAN CITY
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,897,230.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, RUBYVILL E TO ALPHA HOMES, BARANGAY 160, CALOOCAN CITY
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,887,505.00
- Contract status: Completed Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING (PHASE 3), CALOOCAN CITY
- Contractor: KING EIGHT BUILDERS AND SUPPLY (37325) / IRONCUE CONSTRUCTION AND SUPPLY INC. (50470)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱97,501,784.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO GITNA, BAR ANGAY 166, CALOOCAN CITY
- Contractor: EIRISH BUILDERS & SUPPLY INC. (33656)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,894,846.50
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - TERTIARY ROADS, DEPARO-BAGUMBONG RD - K0020 + (-270) - K0020 + 0 38
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-22
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱14,489,813.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, BARANGAY 159, CALOOCAN CITY
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,721,993.00
- Contract status: Completed Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG UGONG VALENZUELA TO MINDANAO AVENUE, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱42,427,144.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, SITIO HULO, B ARANGAY 171, CALOOCAN CITY
- Contractor: PERSAN CONSTRUCTION, INC. (FORMERLY: PERSAN CONST. (2852)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,625,636.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BUILDING 2, BARA NGAY 167, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,822,395.50
- Contract status: Completed Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COV ERED COURT), BARANGAY 177, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,926,423.75
- Contract status: Completed Report
- IMPROVEMENT OF ROAD INCLUDING DRAINAGE SYSTEM ALONG RIVE RA ST., BARANGAY 163, CALOOCAN CITY
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,724,106.00
- Contract status: Completed Report
- REHABILITATION OF ROAD AND DRAINAGE AT RIVERA BUKID, BRG Y. 163, CALOOCAN CITY
- Contractor: WAWAO BUILDERS (46535)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,225,032.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE - SECONDARY ROAD C-3 ROAD - K0008 + (-320) - K0008 + 129
- Contractor: AIC CONSTRUCTION SERVICES (53710)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱7,368,348.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE - SECONDARY ROADS C-3 ROAD - K000 8 + 129 - K0008 + 673
- Contractor: AIC CONSTRUCTION SERVICES (53710)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱9,396,271.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE - SECONDARY ROADS C-3 ROAD - K001 1 + 025 - K0011 + 321
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱4,805,788.50
- Contract status: Completed Report
- CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALON G NATIONAL ROADS - SECONDARY ROADS, C-3 ROAD, K0010 + (-362) - K0010 + 132< /span>
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱9,623,633.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, VILLA REFORM III , BARANGAY 167, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,817,529.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT)), PHASE 9, PACKAGE 7A, BARANGAY 176, BAGONG SILANG, CALOOCAN CITY, METRO MAN ILA
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,574,718.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, ST. JOHN VILLAS, BARANGAY UGONG, VALENZUELA CITY
- Contractor: GLOBALCRETE BUILDERS INC. (40796)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,882,381.00
- Contract status: Completed Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BAR ANGAY HALL), BARANGAY 148, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,931,649.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BUILDING 1, BARA NGAY 167, CALOOCAN, MANILA
- Contractor: PHEAMES COMMUNITY CONSTRUCTION CORPORATION (31773)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,480,164.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG DO C3 91A AURORA BRGY. 188, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,615,208.00
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY A ND REGULATORY SIGNS AND PAVEMENT MARKINGS-CENTERLINES, EDGE LINES NCLUDING PROFILE EDGE LINES, ALONG EPIFANIO DELOS SANTOS AVE (EDSA) - K0010 + (-822) - K0010 + 178, BRGY. 87, CALOOCAN CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,024,606.56
- Contract status: Completed Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRG Y. 159, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,761,137.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 168, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,831,527.50
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAGRADO, BARANGA Y 167, CALOOCAN CITY
- Contractor: ROADMAX CONSTRUCTION CORPORATION (34397)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,828,771.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER) VILLA CRYSTAL, PHASE 3, BAGUMBONG DULO, BRGY. 171, CALOOCAN CITY
- Contractor: MK ZACK BUILDERS CORP. (42193)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,832,043.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 143, CA LOOCAN CITY
- Contractor: ROADMAX CONSTRUCTION CORPORATION (34397)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,761,124.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CAPITOL PARK H OMES I, BRGY. 179, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-01
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,720,899.00
- Contract status: Completed Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT A LMAR, BRGY. 177, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-01
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,760,953.00
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY A ND REGULATORY SIGNS AND PAVEMENT MARKINGS ALONG RIZAL AVE EXT. - K0007 + 35 9 - K0008 + 410, BARANGAY 106, CALOOCAN CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱3,694,366.00
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE AND PAVEMENT MARKIN GS ALONG 7TH AVE EAST - K0008 + (-236) - K0008 + 746, BARANGAY 121, CALOOCA N CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,121,855.50
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - PRIMARY ROADS MACARTHUR H-WAY - K0015 + 823 - K0015 + 973
- Contractor: DSA PRIME BUILDERS CORPORATION (51697)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-21
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱20,411,406.00
- Contract status: Completed Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - SECONDARY ROADS, KAYBIGA RD - K0019 + (-328) - K0019 + (-128)
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-03
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱9,737,927.00
- Contract status: Completed Report
- REHABILITATION OF ROADS AND DRAINAGE ALONG SIKAP MIRAMON TE, BRGY. 180, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,227,320.00
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE, PAVEMENT MARKINGS, AND IMPROVE SIGHT DISTANCE-CLEAR OBSTRUCTION ALONG MAC ARTHUR HIGHWAY - K0 011 + (-362) - K0011 + 638 BARANGAY MARULAS, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱3,653,586.25
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. 179, CLAOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-01
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,748,405.00
- Contract status: Completed Report
- CONSTRUCTION OF ROADS AND DRAINAGE ALONG AMPARO SUBDIVIS ION, BARANGAY 179, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-04
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱7,699,071.50
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY 184, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,870,291.50
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL EX TENSION), BARANGAY 184, CALOOCAN CITY
- Contractor: DSA PRIME BUILDERS CORPORATION (51697)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,878,205.50
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , LALOMA, BARANGAY 178, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱7,778,148.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG BARANGAY 180, CA LOOCAN
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,224,250.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (STA. RITA COVE RED COURT), BARANGAY 188, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱5,855,794.00
- Contract status: Completed Report
- CONSTRUCTION OF ROAD AND DRAINAGE ALONG DULO CONCEPCION, BRGY. 188, CALOOCAN CITY
- Contractor: IM CONSTRUCTION CORPORATION (20074)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,547,903.00
- Contract status: Completed Report
- CONSTRUCTION OF DRAINAGE SYSTEM ALONG BARANGAY 61, CALOO CAN CITY
- Contractor: DMLC BUILDERS (36650)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-01
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱23,958,668.00
- Contract status: Completed Report
- INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY A ND REGULATORY SIGNS AND PAVEMENT MARKINGS ALONG SAMSAON RD - K0010 + (-745) - K0010 + 255, BARANGAY 80, CALOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱3,775,600.25
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE - PRIMARY ROADS - EPIFANIO DELOS SANTOS AVE (EDSA) - K0010 + (-920) - K0010 + (-844), K0010 + (-942) - K0010 + (-920)
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱4,802,675.50
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 187, CALOO CAN CITY
- Contractor: 5-1 CONSTRUCTION CORPORATION (33605)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,682,785.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, AMPARO NATURE'S PARK, BRGY. 179, CALOOCAN CITY
- Contractor: JOSE CRIS BUILDERS (31042)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,835,507.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , BARANGAY 187, CALOOCAN CITY
- Contractor: 5-1 CONSTRUCTION CORPORATION (33605)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,760,761.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, A. FERNANDO, BAR ANGAY MARULAS, VALENZUELA CITY
- Contractor: GLOBALCRETE BUILDERS INC. (40796)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱10,699,091.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , BARANGAY 186, CALOOCAN CITY
- Contractor: AVE-MIRA CONSTRUCTION AND TRADING (42759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-28
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱5,854,535.50
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 183, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,757,731.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE - PRIMARY ROADS - BONIFACIO MONUM ENT CIRCLE - K0009 + (-014) - K0009 + 011.50, K0009 + 047 - K0009 + 153, K0 009 + 194 - K0009 + 209
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-02
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱3,457,048.25
- Contract status: Completed Report
- CONSTRUCTION OF WATER SUPPLY SYSTEM, BRGY. BIGNAY, VALEN ZUELA CITY
- Contractor: KING CLOVER CONSTRUCTION INC. (57120)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-01
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,874,847.50
- Contract status: Completed Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG A . PABLO ST., (PHASE II), BARANGAY GEN. T DE LEON, VALENZUELA CITY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱14,178,003.00
- Contract status: On-Going Report
- REHABILITATION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG B AHAYANG PAG-ASA (PHASE III), BARANGAY MAYSAN, VALENZUELA CITY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱27,835,502.00
- Contract status: On-Going Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG BI GLANG AWA STREET, CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱46,833,584.00
- Contract status: On-Going Report
- CONSTRUCTION OF DRAINAGE SYSTEM ALONG KARUHATAN SERVICE ROAD NLEX (PHASE III), BARANGAY KARUHATAN, VALENZUELA CITY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱14,429,476.00
- Contract status: On-Going Report
- CONSTRUCTION OF DRAINAGE SYSTEM ALONG MAYSAN SERVICE ROA D NLEX (PHASE III), BARANGAY MAYSAN, VALENZUELA CIY
- Contractor: RWORKMATE CONSTRUCTION (48590)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱14,426,486.00
- Contract status: On-Going Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG A. MABINI ST., CALOOCAN CITY
- Contractor: E.M. CUERPO, INC. (30963) / AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,278,600.00
- Contract status: On-Going Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COV ERED COURT), BARANGAY PASO DE BLAS, VALENZUELA CITY
- Contractor: E.L. TORRES CONSTRUCTION AND TRADING INC. (FORMERLY : E. L. TORRES CONSTRUCTION & TRADING (31406)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱24,344,012.00
- Contract status: On-Going Report
- CONSTRUCTION OF DPWH METRO MANILA 3RD DEO OFFICE BUILDIN G (PHASE II), APDC-BAI COMPOUND R. VALENZUELA EXTENSION. BRGY. MARULAS, VAL ENZUELA CITY
- Contractor: MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS (17701)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-08
- Fund source: Regular Infra - GAA 2024 LP
- Contract price: ₱48,500,188.00
- Contract status: On-Going Report
- CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG BAR ANGAYS 86, 87, AND 94, (PHASE 2), CALOOCAN CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-05-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,622,946.00
- Contract status: On-Going Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, DELA COSTA COM MUNITY, BARANGAY 179, CALOOCAN CITY
- Contractor: DSA PRIME BUILDERS CORPORATION (51697)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,878,902.00
- Contract status: On-Going Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 2N D STREET, CALOOCAN CITY
- Contractor: E.M. CUERPO, INC. (30963) / AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,183,776.00
- Contract status: On-Going Report
- IMPROVEMENT OF ROAD, LIBIS 1 & 2, PHASE II, BARANGAY CANUMAY EAST, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-02-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱48,505,504.00
- Contract status: On-Going Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) , TALA GLORIETTA, PHASE III, BARANGAY 188, CALOOCAN CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-11
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,744,533.00
- Contract status: On-Going Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY 185, CALOOCAN CITY
- Contractor: JOSE CRIS BUILDERS (31042)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,751,306.00
- Contract status: On-Going Report
- CONSTRUCTION OF PUMPING STATION WITH FLOOD CONTROL WALL (PHASE 2) AT BAHAYANG PAG-ASA, BARANGAY MAYSAN, VALENZUELA CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-10
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱53,092,496.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), AMPARO ROTONDA, BARANGAY 179, CALOOCAN CITY
- Contractor: JOSE CRIS BUILDERS (31042)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱48,752,644.00
- Contract status: On-Going Report
- CONSTRUCTION OF NEW ADMINISTRATIVE BUILDING - UNIT 1, BU REAU OF ANIMAL INDUSTRY - DEPARTMENT OF AGRICULTURE (PHASE 2), MARULAS, VAL ENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-23
- Fund source: Regular Infra - GAA 2024 LP
- Contract price: ₱29,194,118.00
- Contract status: On-Going Report
- CONSTRUCTION OF NEW ADMINISTRATIVE BUILDING - UNIT 2, BU REAU OF ANIMAL INDUSTRY - DEPARTMENT OF AGRICULTURE (PHASE 2), MARULAS, VAL ENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-23
- Fund source: Regular Infra - GAA 2024 LP
- Contract price: ₱29,194,494.00
- Contract status: On-Going Report
- CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHA SE 10), VALENZUELA CITY
- Contractor: J. SIMEON CONSTRUCTION (31867) / MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-07-08
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,085,136.00
- Contract status: On-Going Report
- CONSTRUCTION OF FLOOD MITIGATION FACILITY (ARKONG BATO R ELIEF PUMPING STATION), BRGY. ARKONG BATO, VALENZUELA CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-23
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,802,832.00
- Contract status: On-Going Report
- ROAD CONCRETING AND DRAINAGE CANAL IN CUERPO ST., BRGY. DALANDANAN, VALENZUELA CITY (PHASE 2)
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,873,100.50
- Contract status: On-Going Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG GEN. T . DE LEON TO UGONG (QUE GRANDE ROAD), VALENZUELA CITY
- Contractor: MSGON CONSTRUCTION CORP. (FORMERLY: MARCOS S. GONZALES CONSTRUCTION COMPANY, INC.) (6421)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱13,496,247.00
- Contract status: On-Going Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG CANUAY EAST TO LAWANG BATO (TRINIDAD, D. BONIFACIO, MALINIS), VALENZUELA CITY
- Contractor: AMIANAN BUILDERS AND TRADING INC. (48143)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱23,116,136.00
- Contract status: On-Going Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG MARULA S TO GEN T. DE LEON (PIO VALENZUELA ROAD-GEN T. DE LEON ROAD), VALENZUELA C ITY
- Contractor: MSGON CONSTRUCTION CORP. (FORMERLY: MARCOS S. GONZALES CONSTRUCTION COMPANY, INC.) (6421)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱12,534,193.00
- Contract status: On-Going Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG PARADA , (SEGMENT 9 PARADA EXIT CAPTAIN CRUZ STREET) VALENZUELA CITY
- Contractor: AGH CONSTRUCTION CORPORATION (46966)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,571,024.00
- Contract status: On-Going Report
- INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG LAWANG BATO-PUNTURIN-BIGNAY (MALINIS ROAD-PUNTURIN ROAD-IBABA ROAD) VALENZUELA CI TY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱25,991,420.00
- Contract status: On-Going Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - TERTIARY ROADS POLO-PUGAD BABOY RD - K0017 + (-184) - K0017 + 00 0, K0017 + (-259) - K0017 + (-184), K0017 + (-265) - K0017 + (259), K0017 + 000 - K0017 + 120
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-08
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱6,984,840.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI PURPOSE BUILDING WITH GROUND IMPRO VEMENTS AT MAHABANG PARANG, BRGY. BIGNAY, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-05
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱11,636,935.00
- Contract status: On-Going Report
- CONSTRUCTION OF A 3-STOREY MULTI-PURPOSE BUILDING (PHASE 3), BARANGAY LAWANG BATO, VALENZUELA CITY
- Contractor: LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR) (29172)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-06
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱29,166,728.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, BARANGA Y LAWANG BATO, VALENZUELA CITY
- Contractor: LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR) (29172)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-02-04
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱97,673,544.00
- Contract status: On-Going Report
- CONSTRUCTION (COMPLETION) OF TOMAS MAUEL COVERED COURT, BRGY. KARUHATAN, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-07
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,746,595.00
- Contract status: On-Going Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PA VED ROADS- TERTIARY ROADS PASOLO-RINCON ROAD K0015 +898 - K0016 + 681
- Contractor: OSCORD BUILDERS CORPORATION (44137)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-05-19
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱39,864,676.00
- Contract status: On-Going Report
- OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS POLO-PUGAD BABOY RD - K0017 + 088 - K0017 + 395
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱19,206,670.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, AMVA, BARANGAY U GONG, VALENZUELA CITY
- Contractor: GLOBALCRETE BUILDERS INC. (40796)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱16,489,825.00
- Contract status: On-Going Report
- CONSTRUCTION OF DRAINAGE ALONG FORTUNE 1, BARANGAY GEN. T. DE LEON, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-06-23
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱9,631,712.00
- Contract status: On-Going Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BAR ANGAY HALL), BARANGAY KARUHATAN, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱24,300,382.00
- Contract status: On-Going Report
- CONSTRUCTION OF PARADA CONVENTION CENTER, BARANGAY PARAD A (PHASE 3), VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-02-18
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱33,765,392.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING) , ROBERTA DE JESUS, ELEMENTARY SCHOOL, BIGNAY, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱33,989,976.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING) , BAGBAGUIN HIGH SCHOOL, MALINIS, BAGBAGUIN, VALENZUELA CITY
- Contractor: C.L. MORALES CONSTRUCTION AND TRADING (38367)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱34,007,300.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING) , LUIS FRANCISCO ELEMENTARY SCHOOL, VEINTE REALES, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱46,614,596.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING) , PUNTURIN ELEMENTARY SCHOOL, PUNTURIN, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱46,638,352.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING) , SILVESTRE LAZARO ELEMENTARY SCHOOL, UGONG, VALENZUELA CITY
- Contractor: TOUGHBUILT CONSTRUCTION & TRADING, INC. (35947) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱46,609,944.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL BUILDING) , BITIK ELEMENTARY SCHOOL, GEN. T. DE LEON, VALENZUELA CITY
- Contractor: C.L. MORALES CONSTRUCTION AND TRADING (38367)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱46,629,376.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDNG, PARADA ELEMENTARY SCHOOL, PARADA, VALENZUELA CITY
- Contractor: J. SIMEON CONSTRUCTION (31867) / MIGHTY CONSTRUCTION & DEVELOPMENT INC. (50253)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱60,151,892.00
- Contract status: On-Going Report
- REHABILITATION OF ROAD AND DRAINAGE ALONG BARANGAYS 16, 18, 20 AND 22, CALOOCAN CITY
- Contractor: AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱38,826,436.00
- Contract status: On-Going Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, KAR UHATAN NATIONAL HIGH SCHOOL, BARANGAY KARUHATAN, VALENZUELA CITY
- Contractor: GLOBALCRETE BUILDERS INC. (40796)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,438,942.00
- Contract status: On-Going Report
- REHABILITATION OF ROAD AND DRAINAGE ALONG BARANGAYS 23, 25, 25, 26, 27 AND 30, CALOOCAN CITY
- Contractor: AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱38,846,012.00
- Contract status: On-Going Report
- CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 8T H AVENUE, PHASE 2, CALOOCAN CITY
- Contractor: WAY MAKER GENERAL CONTRACTOR OPC (52351)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-21
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱28,717,704.00
- Contract status: On-Going Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, TOM AS MANUEL SUBDIVISION, BARANGAY KARUHATAN, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱19,440,116.00
- Contract status: On-Going Report
- REHABILITATION OF MULTI-PURPOSE FACILITY, GLORIETTA TALA , BRGY. 188, CALOOCAN CITY (PHASE 2)
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-02-18
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱39,015,636.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SMMI, PHASE 2, BARANGAY 178, CALOOCAN CITY
- Contractor: A.L. LUCERO CONSTRUCTION SERVICES (48004)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱7,806,262.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAPULANG LUPA, V ALENZUELA CITY
- Contractor: DREAMWORX BUILDER & TRADING, INC. (34004) / MILES TRADING AND CONSTRUCTION (44017)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-05-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱73,356,048.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARULAS, VALENZU ELA CITY
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-05-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱72,940,608.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, (3S COMPLETION, LEARNING CENTER, VALACE) GEN. T. DE LEON VALENZUELA CITY
- Contractor: C.B. TAMPENGCO CONSTRUCTION & SUPPLY (18505)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱77,705,112.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE I), (PNP/B FP) SAMSON ROAD, BARANGAY 80, CALOOCAN CITY
- Contractor: MONOCRETE CONSTRUCTION PHILIPPINES, INC. (37811)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-30
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱200,001,696.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING WITH GROUND IMPRO VEMENT (PHASE 6) PCKG 1, BRGY. CANUMAY WEST, VALENZUELA CITY
- Contractor: MILES TRADING AND CONSTRUCTION (44017) / OSCORD BUILDERS CORPORATION (44137)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱97,511,112.00
- Contract status: On-Going Report
- CONSTRUCTION OF PUP ACADEMIC BUILDING (PHASE 4), CALOOCA N CITY CAMPUS, CALOOCAN CITY
- Contractor: KING EIGHT BUILDERS AND SUPPLY (37325) / IRONCUE CONSTRUCTION AND SUPPLY INC. (50470)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱173,903,456.00
- Contract status: On-Going Report
- CONSTRUCTION OF RETAINING WALL AT DISIPLINA VILLGAE (PHA SE 2), BARANGAY UGONG, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-22
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱24,007,030.00
- Contract status: On-Going Report
- PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG C-3 ROAD, K0009 + 000 - K0008 - 265
- Contractor: GREAT PACIFIC BUILDERS AND GEN. CONTRACTOR INC. ([REVOKED] 45914)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱43,237,324.00
- Contract status: On-Going Report
- PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG C-3 ROAD , K0010 + (-362) - K0010 + 182
- Contractor: AYLAN CONSTRUCTION & TRADING (11884)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱24,054,154.00
- Contract status: On-Going Report
- CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALON G NATIONAL ROADS - SECONDARY ROADS, C-3 ROAD, K0011 + (-319) - K0011 + 681, K0011 + 710 - K0011 + 778
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-23
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱19,227,200.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MAYSAN, VA LENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-02-19
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱29,176,654.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 144, CA LOOCAN CITY
- Contractor: JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS (24748)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-10-18
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱29,164,210.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, PASOLO, VALENZUE LA CITY
- Contractor: C.L. MORALES CONSTRUCTION AND TRADING (38367)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱43,668,600.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY UGONG, VALENZUELA CITY
- Contractor: GLOBALCRETE BUILDERS INC. (40796)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-09-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱6,818,921.50
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (TESDAMAN SPORT C OMPLEX), SAMSON ROAD, BARANGAY 80, CALOOCAN CITY, METRO MANILA
- Contractor: MONOCRETE CONSTRUCTION PHILIPPINES, INC. (37811)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-10-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱146,342,384.00
- Contract status: On-Going Report
- INSTALLATION/ APPLICATION OF SIGNAGE AND PAVEMENT MARKIN GS, AND ZEBRA PEDESTRIAN CROSSING ALONG A. MABINI ST. - K0008 + 855 - K0009 + 917, BARANGAY 13, CALOOCAN CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-07-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱3,572,507.75
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVENTION CENTER ), BARANGAY MARULAS (PHASE 3), VALENZUELA CITY
- Contractor: LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR) (29172)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱33,822,472.00
- Contract status: On-Going Report
- CONSTRUCTION OF COMELEC BUILDING, PHASE II, CALOOCAN CIT Y
- Contractor: KING EIGHT BUILDERS AND SUPPLY (37325)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-21
- Fund source: Regular Infra - GAA 2024 LP
- Contract price: ₱48,246,816.00
- Contract status: On-Going Report
- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BAR ANGAY MARULAS, VALENZUELA CITY
- Contractor: LARSEN-DUTCHER CONSTRACTOR CORPORATION (FORMERLY:LARSEN-DUTCHER CONSTRACTOR) (29172)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱38,924,832.00
- Contract status: On-Going Report
- INSTALLATION/ APPLICATION OF SIGNAGE, PAVMENT MARKINGS, AND ZEBRA PEDESTRIAN CROSSING ALONG 10TH AVE EAST - K0009 + (-857)) - K0009 + 143, BARANGAY 103, CALOOCAN CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,088,059.00
- Contract status: On-Going Report
- INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY A ND REGULATORY SIGNS AND PAVEMENT MARKINGS ALONG RIZAL AVE EXT. - K0009 + 51 3 - K0008 + 547, BARANGAY 68, CALOOCAN CITY
- Contractor: TWO DIMENSION CONSTRUCTION (39410)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-11-01
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱3,697,387.00
- Contract status: On-Going Report
- REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAV ED ROADS - PRIMARY ROADS MAC ARTHUR H-WAY - K0011 + 521 - K0012 + 836
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-02-04
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱23,920,034.00
- Contract status: On-Going Report
- PREVENTIVE MAINTENANCE - PRIMARY ROADS MACARTHUR H-WAY - K0011 + (-297) - K0011 + 014, K0011 + (-447) - K0011 + (-297), K0011 + 014 - K0011 + 521
- Contractor: PASCAL CONSTRUCTION (34168)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-01-05
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱16,124,107.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, (3S PINALAGAD BU ILDING, FIRE, HEALTH AND DAYCARE) MALINTA, VALENZUELA CITY
- Contractor: DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES) (16759)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-30
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱77,689,632.00
- Contract status: On-Going Report
- INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY A ND REGULATORY SIGNS, PAVEMENT MARKINGS-CENTERLINES, EDGE LINES INCLUDING PR OFILE EDGE LINES, AND MEDIAN STRIP ALONG GENERAL SAN MIGUEL STREET - K0011 + (-732) - K0011 + 268, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-08-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,103,594.50
- Contract status: On-Going Report
- CONSTRUCTION OF DRAINAGE STRUCTURE ALONG LANGARAY STREET LEADING TO PERIPHERAL CANAL, CALOOCAN CITY
- Contractor: FRAMECON BUILDERS (22482)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-10-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱48,041,364.00
- Contract status: On-Going Report
- PREVENTIVE MAINTENANCE - PRIMARY ROADS EPIFANIO DELOS SA NTOS AVE 9EDSA) - K0010 + 032 - K0010 + 214
- Contractor: SAN IGMEDIO BUILDERS INCORPORATED (36167)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2024-12-22
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱8,968,187.00
- Contract status: On-Going Report
- PREVENTIVE MAINTENANCE - PRIMARY ROADS MACARTHUR H-WAY - K0017 + 249 - K0017 + 388
- Contractor: DSA PRIME BUILDERS CORPORATION (51697)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-02
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱14,540,095.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, GUADANOVILLE SUB D., CALOOCAN NORTH, CALOOCAN CITY
- Contractor: OSCORD BUILDERS CORPORATION (44137)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-07-30
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱48,755,536.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAON, VEINTE REA LES, VALENZUELA CITY (SHFC)
- Contractor: J. SIMEON CONSTRUCTION (31867) / KING CLOVER CONSTRUCTION INC. (57120)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2026-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱292,243,648.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, (DEPED BUILDING) MALINTA, VALENZUELA CITY
- Contractor: J. SIMEON CONSTRUCTION (31867) / NOVA VENTUS CONSTRUCTION INC. (53730)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2026-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱219,407,072.00
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, DEKADAVILLE, BAR ANGAY BAGBAGUIN, VALENZUELA CITY
- Contractor: DAUNGAN CONSTRUCTION DEV'T. & GEN. SUPPLIES CO., INC. (35024)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-05-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,861,415.50
- Contract status: On-Going Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, ACES CODE, BARAN GAY UGONG, VALENZUELA CITY
- Contractor: GLOBALCRETE BUILDERS INC. (40796)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,874,204.50
- Contract status: On-Going Report
- RAINWATER COLLECTORS IN PUBLIC FACILITIES, CALOOCAN AND VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-03-17
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,817,654.50
- Contract status: On-Going Report
- CONSTRUCTION OF ROAD WITH DRAINAGE, TAGALAG, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-12-17
- Fund source: Regular Infra - GAA 2023 Augmentation
- Contract price: ₱38,470,520.00
- Contract status: On-Going Report
- IMPROVEMENT OF ROAD AND DRAINAGE, ESTEBAN SOUTH (PHASE 2) BRGY. DALANDANAN, VALENZUELA CITY
- Contractor: TM ABAD CONSTRUCTION CORP. (FOR: TM ABAD CONST.) (9302)
- Implementing Agency: National Capital Region - Metro Manila 3rd District Engineering Office
- Region: National Capital Region
- Contract effectivity:
- Contract expiry: 2025-04-21
- Fund source: Regular Infra - GAA 2023 Augmentation
- Contract price: ₱17,310,016.00
- Contract status: On-Going Report