Infrastructure Projects in Negros Island Region — Negros Island Region - Negros Oriental 2nd District Engineering Office, 2024
This page lists public infrastructure projects implemented by Negros Island Region - Negros Oriental 2nd District Engineering Office in Negros Island Region during 2024. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962) | 12 | ₱566,231,344.00 |
| UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336) | 9 | ₱492,187,400.00 |
| DRAGONHART CONSTRUCTION ENTERPRISE, INC. (31725) / KAEL CONSTRUCTION AND SUPPLY (49152) | 2 | ₱287,204,496.00 |
| ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762) | 3 | ₱287,139,088.00 |
| R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556) | 6 | ₱156,004,650.00 |
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/ OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MAG-ABO TO BARANGAY TAMBOJANGI N, AMLAN, NEGROS ORIENTAL
- Contractor: RACCT CONSTRUCTION AND TRADING (35641)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: MULTI-PURPOSE BUILDINGS/ F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY TAMBOJANGIN, AMLAN, NEGROS ORIENTAL
- Contractor: BIGFOOT CONSTRUCTION AND SUPPLY (24769)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-27
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: MULTI-PURPOSE BUILDINGS/ F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY JUGNO, AMLAN, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM: MULTI-PURPOSE BUILDINGS/ F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY BIO-OS, AMLAN, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-28
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,970,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDI NGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY PAL-EW TO BARANGAY STO. NI C3 91O, TANJAY CITY, NEGROS ORIENTAL
- Contractor: DUMDUMA CONSTRUCTION AND TRADING CORPORATION (37256)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-10
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,900,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY 2, BAIS CITY, NEGROS ORIENTAL
- Contractor: A. CABIJE CONSTRUCTION SERVICES AND SUPPLY CORP. (42834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-10
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,970,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY CONSOLACION, BAIS CITY, NEGROS ORIENTAL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,902,716.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY NAPASUAN, MABINAY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-02
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY PANTAO, MABINAY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-14
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY BUGNAY, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-14
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,959,914.25
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY 4, TANJAY CITY, NEGROS ORIENTAL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,970,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF ACCESS ROAD LEADING TO TANJAY BOARDWALK, TANJAY CITY, NEGROS ORIENTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-29
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱19,300,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - TINAPAYAN - CAMBAJAO ROAD LEADING TO PUNCAK, TANAWAN, BALUGO, SIBULAN, NEGROS ORIEN
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD FROM SITIO PALANGGING LEADING TO TINDOG BATO LAKE, BAIS CITY, NEG. OR.
- Contractor: 8G CONSTRUCTION AND GENERAL SERVICES (35783)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD FROM CROSSING TABUAC T O CANTUMBOL DOS FALLS, BAIS CITY, NEGROS ORIENTAL
- Contractor: BIGFOOT CONSTRUCTION AND SUPPLY (24769)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD LEADING TO BUGSOK FALL S, MABINAY, NEGROS ORIENTAL
- Contractor: VESA ENGINEERING AND CONSTRUCTION (32334)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS RO AD LEADING TO NEGROS ORIENTAL STATE UNIVERSITY (MABINAY CAMPUS) GOING TO SI TIO BANGKAL TO PROPER OLD NAMANGKA LEADING TO CAYASO CAVE, BRGY. POBLACION, MABINAY, NEGROS ORIENTAL
- Contractor: R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,750,890.00
- Contract status: Completed Report
- (ROAD LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRAST RUCTURE PROGRAM - ROLL-IT) - SITIO CANTUGOT, BRGY. SAB-AHAN CONNECTING TO L CC DUYAN NG PAG-IBIG FOUNDATION INC. FARM SCHOOL AND BAIS-DUMAGUETE NATIONA L ROAD IN SUPPORT OF THE COFFEE INDUSTRY, BAIS
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-30
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱14,700,000.00
- Contract status: Completed Report
- (ROAD LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRAST RUCTURE PROGRAM - ROLL-IT) - SITIO NALANDAN - SITIO CAMBAYUGON CONNECTING N ATIONAL HIGHWAY (BOUNDARY TAMISU) IN SUPPORT OF CACAO PROCESSING INDUSTRY, BAIS CITY, NEGROS ORIENTAL
- Contractor: BIGFOOT CONSTRUCTION AND SUPPLY (24769)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-30
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱14,700,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY SAN MIGUEL, TANJAY CITY, NEGROS ORIENTAL
- Contractor: FIRST GRANDEUR BUILDERS INC. (FORMERLY: FIRST GRANDEUR BUILDERS) (35388)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,970,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY BULWANG, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/I MPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONSTRUCTION OF ACCESS ROAD LEADING TO TUGAS FALLS, BRGY. SAB-AHAN, BAIS CITY, NEGROS
- Contractor: 8G CONSTRUCTION AND GENERAL SERVICES (35783)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-10
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱19,300,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/I MPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - BAIS - CAMBAGAHAN ROAD LEADING TO NI LUDHAN FALLS, BAIS CITY, NEGROS ORIENTAL
- Contractor: R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION (COMPLETION) OF MULTI-PURP OSE BUILDING, NORTH POBLACION, BARANGAY POBLACION, MABINAY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,964,984.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY 6, TANJAY CITY, NEGROS ORIENTAL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-17
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FA CILITIES - CONSTRUCTION OF ROAD, BARANGAY TANGCULOGAN, BAIS CITY, NEGROS OR IENTAL
- Contractor: FIRST GRANDEUR BUILDERS INC. (FORMERLY: FIRST GRANDEUR BUILDERS) (35388)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-28
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY ENRIQUE VILLANUEVA, SIBULAN, NEGROS ORIENTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-06
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY JANTIANON, AMLAN, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-16
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPO SE BUILDING, BARANGAY MABUNAO, BAIS CITY, NEGROS ORIENTAL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY PANAM-ANGAN, BAIS CITY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-14
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SAB-AHAN, BAIS CITY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-14
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY HIMOCDONGON, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,959,868.12
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY LUMBANGAN, MABINAY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-26
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,964,570.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY CANSAL-ING, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,959,029.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILD ING, BARANGAY CANGGOHOB, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,943,184.25
- Contract status: Completed Report
- (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - SILAB BAR ANGAY ROAD 1 LEADING TO KAN-UNTOL/ PASALAN FALLS, PUROK, BOUGAINVILLA, ROSE S, SANTAN, CALACHUCHI & WATER SHED AREA, BRGY. SILAB, AMLAN, NEGROS ORI ENTAL
- Contractor: BIGFOOT CONSTRUCTION AND SUPPLY (24769)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY 5, TANJAY CITY, NEGROS ORIENTAL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF ACCESS ROAD LEADING TO BAHIA DE BAIS, DEWEY ISLAND, BAIS CITY, NEG.OR
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱19,300,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF ACCESS ROAD LEADING TO SULFUR LAGOON, BRGY. SAN MIGUEL, TANJAY CITY
- Contractor: MIGHTY HOK SUMMIT CONSTRUCTION & DEVELOPMENT CORP. (43834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-18
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱19,300,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY POBLACION, AMLAN, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY STA. CRUZ NUEVO, TANJAY CITY, NEGROS ORIENTAL
- Contractor: FIRST GRANDEUR BUILDERS INC. (FORMERLY: FIRST GRANDEUR BUILDERS) (35388)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-27
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPO SE BUILDING, BARANGAY CAMBANJAO, BAIS CITY, NEGROS ORIENTAL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-25
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACI LITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLO OD CONTROL DIKE, BARANGAY PANALAAN, BAIS CITY
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-21
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱9,800,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTUR E AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NOVA LLAS RIVER, BARANGAY STA. CRUZ VIEJO, TANJAY CITY
- Contractor: DRAGONHART CONSTRUCTION ENTERPRISE, INC. (31725) / KAEL CONSTRUCTION AND SUPPLY (49152)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-28
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱142,454,496.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACIL ITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF TA MOGONG RIVER CONTROL STRUCTURE, BAIS CITY, NEGROS
- Contractor: QM BUILDERS (30743)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-05
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱115,800,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, CONSTRUCT ION OF NAMANGYAN RIVER CONTROL, MABINAY, NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-30
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱87,611,384.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY BAGTIC, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-16
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,964,689.25
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTU RE AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AML AN RIVER, BARANGAY TAMBUHANGIN, NEGROS ORIENTAL
- Contractor: DRAGONHART CONSTRUCTION ENTERPRISE, INC. (31725) / KAEL CONSTRUCTION AND SUPPLY (49152)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-12-18
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱144,750,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY INAPOY, MABINAY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-04
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,960,614.75
- Contract status: Completed Report
- (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRAS TRUCTURE PROGRAM-ROLL-IT)-E.J. BLANCO ROAD CONNECTING TO THE DUMAGUETE NORT H ROAD AND FLORES AVENUE IN SUPPORT OF DUMAGUETE CITY FOOD INDUSTRY, DUMAGU ETE CITY, NEGROS ORIENTAL
- Contractor: A. CABIJE CONSTRUCTION SERVICES AND SUPPLY CORP. (42834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-26
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱19,600,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTU RE AND DRAINAGE SYSTEMS - CONSTRUCTION OF CALABNUGAN CIS FLOOD/ SLOPE PROTE CTION WORKS/RIVER SILL, SIBULAN, NEGROS ORIENTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-09-05
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱19,600,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, SIBULAN HIGH SCHOOL, BRGY. POBLACION, SIBULAN, NEGROS ORIENTAL
- Contractor: RACCT CONSTRUCTION AND TRADING (35641)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY CAMANJAC, DUMAGUETE CITY, NEGROS ORIENTAL< /li>
- Contractor: C. LARA CONSTRUCTION (17304)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPO SE BUILDING, BARANGAY TACLOBO, DUMAGUETE CITY, NEGROS ORIENTAL
- Contractor: C. LARA CONSTRUCTION (17304)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-30
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,941,183.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MABINAY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-30
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,900,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRI MARY ROADS - BAIS-KABANKALAN ROAD K0061+796 - K0063+093, MABINAY, NEGROS OR IENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-19
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱29,773,380.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-BAIS-KABANKALAN ROAD- K0067+277-K0069+000, MABINAY, NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-01
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱41,086,500.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRI MARY ROADS - BAIS-KABANKALAN ROAD K0085+848 - K0086+301, MABINAY, NEGROS OR IENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-08
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱20,109,600.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY R OADS-DUMAGUETE NORTH ROAD-K0000+308-K0001+810, DUMAGUETE CITY, NEGROS ORIEN TAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-03
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱42,999,460.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY R OADS-DUMAGUETE SOUTH ROAD-K0000+383-K0001+270, DUMAGUETE CITY, NEGROS ORIEN TAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-15
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱28,474,880.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-BAYAWAN-MABINAY ROAD-K0144+000-K0145+036, K0146+801-K0147+780, MABINA Y, NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-02
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱42,286,020.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SEC ONDARY ROADS - STA. CATALINA - PAMPLONA - TANJAY CITY - K0035+860 - K0036+2 17, K0037+408 - K0038+940, PAMPLONA, NEGROS ORIEN
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-27
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱41,064,940.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FA CILITIES-CONCRETING OF ROAD, BRGY. SAN ANTONIO TO BRGY. CALABNUGAN, SIBULAN , NEGROS ORIENTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-09
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FA CILITIES-CONCRETING OF ROAD, BRGY. BAJUMPANDAN, DUMAGUETE CITY, NEGROS ORIE NTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-10
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, JILOCON BR. (CANTILEVERED) (B00080NR) ALONG DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KAB ANKALAN), NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-09-20
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱11,270,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FU ND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROADWAY LIGHTING ALONG DUMAGUETE NORTH RD (DUMAGUETE - JCT BAIS - KABANKALA N) (S00353NR) - K0006+1250-K0006+1350, NEGROS ORI
- Contractor: RACCT CONSTRUCTION AND TRADING (35641)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-15
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,048,600.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FU ND-MOTOR VEHICLE USERS CHARGE(MVUC) AS PER R.A. 11239- INSTALLATION/APPLICA TION/CONSTRUCTION OF SIGNAGE, PAVEMENT MARKINGS/ROADWAY LIGHTING ALONG DUMA GUETE NORTH ROAD (DUMAGUETE-JCT. BAIS-KABANKALAN)
- Contractor: RACCT CONSTRUCTION AND TRADING (35641)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,470,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - PRIMARY ROAD S - BAIS-KABANKALAN RD - K0096+381 - K0096+904, NEGROS ORIENTAL
- Contractor: H.L.J CONSTRUCTION & ENTERPRISES (18080)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-30
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱33,429,800.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SEC ONDARY ROADS-STA.CATALINA-PAMPLONA-TANJAY CITY-K0052+440-K0056+820, NEGROS ORIENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-05
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPG RADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH ROAD (DUMAGUETE- JCT.BAIS-KABANKALAN)K0025+238-K0026+305,K0027+420
- Contractor: NALE CONSTRUCTION (18552) / RICHFIELD BUILDERS, INC. (FORMERLY: RICHFIELD BUILDERS) (24525)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-01-11
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱83,955,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTIO N/UPGRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH ROAD (DUMAG UETE-JCT BAIS-KABANKALAN) - K0002+084-K0002+863
- Contractor: TRINITYCAD CORPORATION (FORMERLY:TRINITY CONSTRUCTION AND DEVELOPMENT) (27755)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-02
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱24,598,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTIO N/UPGRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH ROAD (DUMAG UETE-JCT BAIS-KABANKALAN) K0041+340-K0042+732, NE
- Contractor: MIGHTY HOK SUMMIT CONSTRUCTION & DEVELOPMENT CORP. (43834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-11
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱45,080,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSRUCTION/UPGR ADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-BAIS-KABANKALAN RD-K0096+381-K009 7+000,NEGROS ORIENTAL
- Contractor: H.L.J CONSTRUCTION & ENTERPRISES (18080)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-28
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱22,932,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FA CILITIES - CONCRETING OF ROAD, BRGY. BANTAYAN, DUMAGUETE CITY, NEGROS ORIET AL
- Contractor: MG CONSTRUCTION (41069)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-15
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE - SECON DARY ROADS- STA. CATALINA-PAMPLONA-TANJAY CITY- K0058+000-K0059+360, NEGROS ORIENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-02
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱30,939,580.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING S/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY STO. NI C3 91O, TANJAY CITY, NE ROS ORIENTAL
- Contractor: MIGHTY HOK SUMMIT CONSTRUCTION & DEVELOPMENT CORP. (43834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,900,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP):ACCESS ROADS AND/OR B RIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS /FACILITIES-REHABILITATION OF ROAD, BRGY.BAHI-AN, TANJAY CITY, NEGROS ORIEN TAL
- Contractor: MIGHTY HOK SUMMIT CONSTRUCTION & DEVELOPMENT CORP. (43834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-03
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱9,900,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FA CILITIES-CONSTRUCTION OF ROAD, BRGY. PANAM-ANGAN, BAIS CITY, NEGROS ORIENTA L
- Contractor: RACCT CONSTRUCTION AND TRADING (35641)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-21
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILD ING, POBLACION WOMEN'S ASSOCIATION CENTER (POWAS), PAMPLONA, NEGROS ORIENTA L
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-08
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FL OOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF TAMOGONG RIV ER CONTROL STRUCTURE, BAIS CITY, NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-02-19
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱96,500,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FL OOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF TANJAY RIVER CONTROL STRUCTURE, TANJAY CITY, NEGROS ORIENTAL
- Contractor: QM BUILDERS (30743)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-12-09
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱39,200,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRU CTION OF FLOOD MITIGATION STRUCTURE ALONG TANJAY RIVER PAMPLONA SECTION, PA MPLONA, NEGROS ORIENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-03-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱99,000,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY R OADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)-K0031+000-K0031+100 1, NEGROS ORIENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱29,400,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY R OADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)-K0039+500-K0040+218 , NEGROS ORIENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱29,400,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY R OADS-DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)-K0040+218-K0041+340 , NEGROS ORIENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-09-02
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱39,200,000.00
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UP GRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-BAIS-KABANKALAN RD-K0093+586-K0 094+000, NEGROS ORIENTAL
- Contractor: HOMEWORLD CONSTRUCTION CORP. (FORMERLY HOMEWORLD E (14725)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-10
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱17,150,000.00
- Contract status: Completed Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDI NGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY 2, BAIS CITY, NEGROS ORIEN TAL
- Contractor: A. CABIJE CONSTRUCTION SERVICES AND SUPPLY CORP. (42834)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-03-20
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,929,369.50
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-P URPOSE BUILDING, BARANGAY 1, DUMAGUETE CITY, NEGROS ORIENTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-04
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,966,614.25
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/F ACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDI NG, BARANGAY CANGMATING, SIBULAN, NEGROS ORIENTAL
- Contractor: ASHLEYKA CONSTRUCTION AND SUPPLIES (41140)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-06
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY TAGPO, BAIS CITY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-27
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,976,167.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY CAMBAGAHAN, BAIS CITY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-15
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,980,000.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION (COMPLETION) OF MULTI-PURPO SE BUILDING, BARANGAY LUYANG, MABINAY, NEGROS ORIENTAL
- Contractor: PER CONSTRUCTION AND SUPPLY (37314)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-05-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱1,974,927.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURI SM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF ACCESS ROAD BRGY. CA NGGOHOB LEADING TO CANTUMBOL DOS FALLS, MABINAY
- Contractor: RICHFIELD BUILDERS, INC. (FORMERLY: RICHFIELD BUILDERS) (24525)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-06-11
- Fund source: Regular Infra - GAA 2024 CP
- Contract price: ₱19,290,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTUR E AND DRAINAGE SYSTEMS - REHABILITATION OF RIVER CONTROL STRUCTURE, BARANGA Y CONSOLACION, BAIS CITY, NEGROS ORIENTAL
- Contractor: SUPREME MEGA STRUCTURE BUILDERS, INC. (38607) / SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION) (11597)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-28
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱114,338,856.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATIO N OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RI VERS - CONSTRUCTION OF ILOG RIVER CONTROL (INTERM
- Contractor: R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-09-25
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱29,252,880.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIV ERSION ROADS, METRO DUMAGUETE DIVERSION ROAD, NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-01-12
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱66,495,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, OCOY BR. (B 00074NR) ALONG DUMAGUETE NORTH RD (DUMAGUETE - JCT BAIS- KABANKALAN), NEGRO S ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962) / R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-12-25
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱29,231,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, CALO BR. (B 00076NR) ALONG DUMAGUETE NORTH ROAD (DUMAGUETE-JCT. BAIS-KABANKALAN), NEGRO S ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962) / RICHFIELD BUILDERS, INC. (FORMERLY: RICHFIELD BUILDERS) (24525)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-26
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱22,230,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, AYUQUITAN ( SAN JOSE) BR. (B00078NR) ALONG DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABAN KALAN), NEGROS ORIENTAL
- Contractor: JAIME B. CHING ENTERPRISES (4256)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-04
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱15,044,484.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FA CILITIES-CONCRETING OF ROAD, BRGY. POLO, TANJAY CITY, NEGROS ORIENTAL
- Contractor: DUMDUMA CONSTRUCTION AND TRADING CORPORATION (37256)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-04-10
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,939,440.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING-PRIMARY ROADS-DU MAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)-K0026+548-K0026+700, NEGRO S ORIENTAL
- Contractor: H.L.J CONSTRUCTION & ENTERPRISES (18080)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-07-29
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱13,473,821.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, TAPON NORTE BR. (B00079NR) ALONG DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN), N EGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962) / TRINITYCAD CORPORATION (FORMERLY:TRINITY CONSTRUCTION AND DEVELOPMENT) (27755)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-13
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱20,963,404.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FU ND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROADWAY LIGHTING ALONG DUMAGUETE NORTH RD (DUMAGUETE - JCT BAIS - KABANKALA N) (S00353NR) - K0011+774-K0012+589, NEGROS ORIEN
- Contractor: RACCT CONSTRUCTION AND TRADING (35641)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-09-15
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱5,458,600.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME1: ENSURE SAFE AND RELIABLE NATION AL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING-PRIMARY ROADS-DUM AGUETE NORTH RD (DUMAGUETE-JCT-BAIS-KABANKALAN)-K0021+973-K0022+538, NEGROS ORIENTAL
- Contractor: R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-04
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱31,440,880.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTIO N/UPGRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUE TE-JCT BAIS-KABANKALAN) K0020+455-K0021+857, NEGR
- Contractor: TRINITYCAD CORPORATION (FORMERLY:TRINITY CONSTRUCTION AND DEVELOPMENT) (27755)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-07
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱44,618,392.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UP GRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH RD(DUMAGUETE-JC T BAIS-KABANKALAN) K0011+228-K0012+589,K0013+226
- Contractor: BIGFOOT CONSTRUCTION AND SUPPLY (24769)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-12-17
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱65,620,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UP GRADING OF DAMAGED PAVED ROAD-PRIMARY ROADS-DUMAGUETE NORTH RD (DUMAGUETE-J CT BAIS-KABANKALAN) K0035+046-K0036+500
- Contractor: R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-10-22
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱46,060,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING-PRIMARY ROADS-BA IS-KABANKALAN RD-K0099+000-K0099+820, NEGROS ORIENTAL
- Contractor: HOMEWORLD CONSTRUCTION CORP. (FORMERLY HOMEWORLD E (14725)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-11-24
- Fund source: Regular Infra - GAA 2024 OO-1
- Contract price: ₱51,418,696.00
- Contract status: On-Going Report
- CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM AT 1) FABIANA G. BANOGON MEMORIAL ELEME NTARY SCHOOL, SITIO CAMANSI, BARANGAY NOVALLAS, TANJAY CITY, NEGROS ORIENTA L 2) GRACIANO BANOGON SR. MEMORIAL HIGH SCHOOL,
- Contractor: DOUBLE J AND T CONSTRUCTION AND SUPPLY CORPORATION (50227)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2024-08-22
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱2,892,759.50
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INF RASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCT URES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SHORE PROTECTION, BARANGAY LOOC TO BARANGAY PIAP
- Contractor: ST. TIMOTHY CONSTRUCTION CORPORATION (39196)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-08-14
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱94,570,016.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INF RASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCT URES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SHORE PROTECTION, BARANGAY LOOC, DUMAGUETE CITY,
- Contractor: J. SIMEON CONSTRUCTION (31867)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-08-14
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱96,500,000.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FU ND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG DUMAGUETE NORTH ROAD, AMLAN, NEGROS ORIE NTAL
- Contractor: ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-04-23
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱98,000,000.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INF RASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCT URES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF LOOC SHORE PROTECTION, LOOC, SIBULAN
- Contractor: LEDA CONSTRUCTION INCORPORATED (12229) / JCW CONSTRUCTION (32161)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-02-12
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱93,605,000.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUC TION OF RIVERBANK PROTECTION STRUCTURE ALONG ILOG RIVER, MABINAY, NEGROS OR IENTAL
- Contractor: UY CONDEV CORPORATION (FORMERLY:UY CONSTRUCTION & (12336)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-02-15
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱98,208,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FL OOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BANICA RIVER CONTROL STRUCTURE, BARANGAY BALUGO, DUMAGUETE CI
- Contractor: HGG BUILDERS & SUPPLY (17824)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-04-22
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱48,250,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FL OOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BANICA RIVER CONTROL STRUCTURE, BARANGAY CANDAU-AY, DUMAGUETE
- Contractor: HGG BUILDERS & SUPPLY (17824)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-01-22
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱47,671,864.00
- Contract status: On-Going Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INF RASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG):SIPAG-FLOOD MITIGATION STRUCT URES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES:CONSTRUCTION OF BULOD RIVER CONTROL(UPSTREAM), MABINAY, NEGROS O
- Contractor: ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-02-13
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱94,569,968.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM (BIP): BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABI LITATION OF TANJAY RIVER CONTROL STRUCTURE, TANJAY CITY, NEGROS ORIENTAL
- Contractor: PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS) (21962)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-05-06
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱99,000,000.00
- Contract status: On-Going Report
- ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES A GAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS -CONSTRUCTION OF NAMANGYAN RIVER CONTROL, BAGTIC
- Contractor: ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-02-13
- Fund source: Regular Infra - GAA 2024 OO-2
- Contract price: ₱94,569,120.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM-MULTI-PURPOSE BUILDINGS/FAC ILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING(S PORTS COMPLEX),MABINAY, NEGROS ORIENTAL
- Contractor: R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: R.E. SINGSON CONSTRUCTION) (24556)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-02-24
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱29,700,000.00
- Contract status: On-Going Report
- BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/F ACILITIES - CONSTRUCTION OF BRIDGE (PHASE I), BARANGAY 1, BASI CITY, NEGROS ORIENTAL
- Contractor: DOUBLE J AND T CONSTRUCTION AND SUPPLY CORPORATION (50227)
- Implementing Agency: Negros Island Region - Negros Oriental 2nd District Engineering Office
- Region: Negros Island Region
- Contract effectivity:
- Contract expiry: 2025-01-16
- Fund source: Regular Infra - GAA 2024 SSP
- Contract price: ₱4,950,000.00
- Contract status: On-Going Report