This page lists public infrastructure projects implemented by Region III - Zambales 2nd District Engineering Office in Region III during 2016. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349) | 7 | ₱229,158,862.00 |
| STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096) | 6 | ₱115,016,190.50 |
| REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) (32842) / ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349) | 2 | ₱78,385,520.00 |
| CHIARA2300 INCORPORATED (8736) | 3 | ₱60,945,079.00 |
| REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) (32842) / THREE W BUILDERS, INC. (10722) | 1 | ₱43,756,236.00 |
- IMPROVEMENT OF STA. RITA RIVER (UPSTREAM), BRGY. STA. RI TA, OLONGAPO CITY
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-08-08
- Fund source: Regular Infra - GAA 2016 MFO-2
- Contract price: ₱42,820,284.00
- Contract status: Completed Report
- IMPROVEMENT OF KALAKLAN RIVER, BRGY. KALAKLAN, OLONGAPO CITY
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-08-02
- Fund source: Regular Infra - GAA 2016 MFO-2
- Contract price: ₱42,822,904.00
- Contract status: Completed Report
- IMPROVEMENT OF PAMATAWAN RIVER, CASTILLEJOS, ZAMBALES
- Contractor: REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) (32842) / THREE W BUILDERS, INC. (10722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-09-01
- Fund source: Regular Infra - GAA 2016 MFO-2
- Contract price: ₱43,756,236.00
- Contract status: Completed Report
- IMPROVEMENT OF MABAYUAN RIVER, BRGY. MABAYUAN, OLONGAPO CITY
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-08
- Fund source: Regular Infra - GAA 2016 MFO-2
- Contract price: ₱18,428,830.00
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. S TA. RITA, OLONGAPO CITY
- Contractor: STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,497,247.25
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT) ILWAS E LEMENTARY SCHOOL, SUBIC, ZAMBALES
- Contractor: THREE W BUILDERS, INC. (10722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,288,473.75
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. B ARRETTO, OLONGAPO CITY
- Contractor: THREE W BUILDERS, INC. (10722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,216,347.00
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGA Y STA. FE, SAN MARCELINO, ZAMBALES
- Contractor: M.V.GUBALLA CONSTRUCTION CORPORATION (FORMERLY: M.V. GUBALLA CONSTRUCTION) (11722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,287,395.75
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGA Y BALAYBAY, CASTILLEJOS, ZAMBALES
- Contractor: RBDIWA BUILDERS AND CONSTRUCTION SUPPLY (36022)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱2,726,258.25
- Contract status: Completed Report
- REHAB. OF DAY CARE CENTER BARANGAY NAGBUNGA, CASTILLEJOS , ZAMBALES
- Contractor: MICKAJETTE CONSTRUCTION AND TRADING (35239)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-03-10
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱470,827.09
- Contract status: Completed Report
- COMPLETION OF MULTI-PURPOSE BUILDING BRGY. LINASIN, SAN MARCELINO, ZAMBALES
- Contractor: MICKAJETTE CONSTRUCTION AND TRADING (35239)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-03-25
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱952,979.31
- Contract status: Completed Report
- REHABILITATION OF SUBIC-PHILSECO ROAD K0141+-462 - K0141 +-407, SUBIC, ZAMBALES
- Contractor: AYSON P.D. CONSTRUCTION (15724)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-02-24
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱1,495,580.88
- Contract status: Completed Report
- REHABILITATION OF DRAINAGE ALONG SUBIC-PHILSECO ROAD K01 42+500 - K0143+222, SUBIC, ZAMBALES
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-09-21
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱42,776,084.00
- Contract status: Completed Report
- REHAB. INCLUDING DRAINAGE OF OLONGAPO-BUGALLON ROAD K015 4+352 - K0154+885, SAN MARCELINO, ZAMBALES
- Contractor: STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-10-02
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱16,242,185.00
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. N EW ILALIM, OLONGAPO CITY
- Contractor: STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,324,746.50
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BUENAVIST A, CASTILLEJOS, ZAMBALES
- Contractor: MICKAJETTE CONSTRUCTION AND TRADING (35239)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱474,884.84
- Contract status: Completed Report
- REHABILITATION OF DAY CARE CENTER BRGY. CENTRAL, SAN MAR CELINO, ZAMBALES
- Contractor: MICKAJETTE CONSTRUCTION AND TRADING (35239)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱760,313.38
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING BRGY. SAN ISIDRO, SAN M ARCELINO, ZAMBALES
- Contractor: STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,335,535.75
- Contract status: Completed Report
- CONST. OF MULTI-PURPOSE BUILDING, BRGY. LUCERO, SAN MARC ELINO, ZAMBALES
- Contractor: MICKAJETTE CONSTRUCTION AND TRADING (35239)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-09
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱2,375,486.50
- Contract status: Completed Report
- COMPLETION OF MULTI-PURPOSE BUILDING (BRGY. HALL) BRGY. SAN ROQUE, CASTILLEJOS, ZAMBALES
- Contractor: AYSON P.D. CONSTRUCTION (15724)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-03-25
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱949,588.75
- Contract status: Completed Report
- REHAB. OF DAY CARE CENTER BRGY. WEST TAPINAC, OLONGAPO C ITY
- Contractor: JAMJLE PROPERTIES (SUBIC) AND DEVELOPMENT CORPORAT (35039)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-03-25
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱768,058.75
- Contract status: Completed Report
- CONST. OF ROADS AT BRGY. GORDON HEIGHTS, OLONGAPO CITY
- Contractor: JAMJLE PROPERTIES (SUBIC) AND DEVELOPMENT CORPORAT (35039)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-03-19
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱3,683,469.25
- Contract status: Completed Report
- REHAB, OF DRAINAGE ALONG NAT'L. ROADS RIZAL AVE.-CHAINAG E 0 - CHAINAGE 2010, OLONGAPO CITY
- Contractor: CHIARA2300 INCORPORATED (8736)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-10-21
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱33,090,152.00
- Contract status: Completed Report
- REHAB. OF DRAINAGE ALONG NAT'L. ROADS OLONGAPO-BUGALLON RD., K0126+000 - K0126+939, OLONGAPO CITY
- Contractor: CHIARA2300 INCORPORATED (8736)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-03
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱15,496,858.00
- Contract status: Completed Report
- OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE OB RD., K 0146+000 - K0147+610, CASTILLEJOS, ZAMBALES
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-08-22
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱41,022,168.00
- Contract status: Completed Report
- WIDENING OF NATIONAL ROADS OB RD. K0140+000 - K0141+500, SUBIC, ZAMBALES
- Contractor: STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-18
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱41,579,224.00
- Contract status: Completed Report
- CONST./IMPVT. OF ACCESS RD., SUBIC-CAWAG-BALAYBAY RD., K 0000+700-K0001+900 & K0005+900-K0007+068
- Contractor: STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) (26096)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-09-19
- Fund source: Regular Infra - GAA 2016 MFO-3
- Contract price: ₱47,037,252.00
- Contract status: Completed Report
- CONCRETING OF SITIO ALUSIIS ROAD BRGY. LOOC, CASTILLEJOS , ZAMBALES
- Contractor: SUBICCON CORPORATION (FORMERLY: SUBCON CORPORATION (25079)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-03-19
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱9,555,119.00
- Contract status: Completed Report
- CONST. OF BRGY. ROAD BRGY. PAMATAWAN, SUBIC, ZAMBALES
- Contractor: JAMJLE PROPERTIES (SUBIC) AND DEVELOPMENT CORPORAT (35039)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-02-24
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱1,900,229.38
- Contract status: Completed Report
- WIDENING OF CALAPACUAN BRIDGE ALONG OLONGAPO-BUGALLON RD ., SUBIC, ZAMBALES
- Contractor: THREE W BUILDERS, INC. (10722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-06-23
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱10,135,005.00
- Contract status: Completed Report
- WIDENING OF MAQUINAYA BRIDGE ALONG OLONGAPO-BUGALLON RD. , OLONGAPO CITY
- Contractor: THREE W BUILDERS, INC. (10722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-06-23
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱12,761,291.00
- Contract status: Completed Report
- WIDENING OF MALINTA BRIDGE ALONG SUBIC-PHILSECO RD. SUB IC, ZAMBALES
- Contractor: CHIARA2300 INCORPORATED (8736)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-23
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱12,358,069.00
- Contract status: Completed Report
- WIDENING OF ANINGWAY BRIDGE ALONG OLONGAPO-BUGALLON RD. SUBIC, ZAMBALES
- Contractor: F.V. SANGALANG CONSTRUCTION (37083)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-23
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱5,468,401.00
- Contract status: Completed Report
- WIDENING OF TALOS BRIDGE ALONG OLONGAPO-BUGALLON RD. SU BIC, ZAMBALES
- Contractor: F.V. SANGALANG CONSTRUCTION (37083)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-23
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱5,468,458.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE CONCRETING OF SUBIC-PHILSECO ROA D, SUBIC, ZAMBALES
- Contractor: HALREY CONSTRUCTION INC. (2267)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-06-30
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱13,201,170.00
- Contract status: Completed Report
- PREVENTIVE MAINTENANCE ASPHALT OVERLAY SM-SAN ANTONIO-S AN NARCISO ROAD K0153+-138 - K0153+701
- Contractor: HALREY CONSTRUCTION INC. (2267)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-05-26
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱12,379,651.00
- Contract status: Completed Report
- CONST. OF SUBIC BYPASS ROAD INCLUDING BRIDGE, SUBIC, ZA MBALES
- Contractor: REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) (32842) / ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-11-22
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱44,658,672.00
- Contract status: Completed Report
- WIDENING OF CABAOANGAN BRIDGE ALONG SUBIC-PHILSECO ROAD , SUBIC, ZAMBALES
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-08-24
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱10,130,016.00
- Contract status: Completed Report
- WIDENING OF MAPANAO BRIDGE ALONG SUBIC-PHILSECO ROAD, S UBIC, ZAMBALES
- Contractor: GVDPM CONSTRUCTION CORP. (FORMERLY: ZM CONSTRUCTIO (9052)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-08-24
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱10,454,480.00
- Contract status: Completed Report
- WIDENING OF SACATIHAN BRIDGE ALONG OLONGAPO-BUGALLON RO AD, SUBIC, ZAMBALES
- Contractor: THREE W BUILDERS, INC. (10722)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-07-25
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱5,476,191.00
- Contract status: Completed Report
- WIDENING OF BULALA BRIDGE ALONG OLONGAPO-BUGALLON ROAD, CASTILLEJOS, ZAMBALES
- Contractor: GVDPM CONSTRUCTION CORP. (FORMERLY: ZM CONSTRUCTIO (9052)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-08-24
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱8,187,495.00
- Contract status: Completed Report
- WIDENING OF PAMATAWAN BRIDGE ALONG OLONGAPO-BUGALLON RO AD, SUBIC, ZAMBALES
- Contractor: REPOLMAN CONSTRUCTION CORP. (FORMERLY: REPOLMAN CONSTRUCTION) (32842) / ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-11-22
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱33,726,848.00
- Contract status: Completed Report
- CONSTRUCTION OFBARANGAY ROAD, BRGY. MATAIN, SUBIC, ZAMB ALES
- Contractor: MICKAJETTE CONSTRUCTION AND TRADING (35239)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-04-27
- Fund source: Regular Infra - GAA 2016 Locally Funded Projects
- Contract price: ₱1,878,359.25
- Contract status: Completed Report
- WIDENING OF CALAPANDAYAN BRIDGE ALONG OLONGAPO-BUGALLON ROAD, SUBIC, ZAMBALES
- Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY) (05349)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2017-01-20
- Fund source: Regular Infra - GAA 2016 MFO-1
- Contract price: ₱31,158,576.00
- Contract status: Completed Report
- CONST. OF RAINWATER COLLECTION SYSTEM (RWCS) OLONGAPO C ITY, SUBIC, CASTILLEJOS, & SAN MARCELINO, ZAM
- Contractor: MCB ZAMORA CONSTRUCTION & SUPPLY (32006)
- Implementing Agency: Region III - Zambales 2nd District Engineering Office
- Region: Region III
- Contract effectivity:
- Contract expiry: 2016-10-23
- Fund source: Regular Infra - GAA 2016 MFO-3
- Contract price: ₱3,248,064.50
- Contract status: Completed Report