Infrastructure Projects in Region IV-B — Region IV-B - Region IV-B, 2019
This page lists public infrastructure projects implemented by Region IV-B - Region IV-B in Region IV-B during 2019. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| EQUI-PARCO CONSTRUCTION COMPANY (14332) | 2 | ₱386,000,000.00 |
| LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) (22465) | 2 | ₱256,779,560.00 |
| PLERM CONSTRUCTION AND DEVELOPMENT CORPORATION (33288) | 1 | ₱154,272,096.00 |
| KATHA BUILDERS & SUPPLIES INC. (34651) | 1 | ₱144,555,584.00 |
| KATHA BUILDERS & SUPPLIES INC. (34651) / ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION) (15199) | 1 | ₱144,413,808.00 |
- CONST. OF MISSING LINK/NEW ROADS, MINDORO ISLAND CIRCUMFER ENTIAL ROAD (PUERTO GALERA - ABRA DE ILOG), KO453+438.00 - KO454+893.00, OC C. MINDORO
- Contractor: MARCBILT CONSTRUCTION, INC. (21844) / SAN MARCELINO BUILDERS, INC. (35983)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2021-11-15
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱144,400,000.00
- Contract status: Completed Report
- CONST. OF MISSING LINK/NEW ROADS, MINDORO ISLAND CIRCUMFER ENTIAL ROAD (PUERTO GALERA - ABRA DE ILOG), KO015+240.00 - KO015+376.00; KO 015+376.00 - KO018+059.00, ORIENTAL MINDORO
- Contractor: B.C. CUERPO CONSTRUCTION CORPORATION (11898)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2021-10-11
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱99,963,192.00
- Contract status: Completed Report
- CONST./IMPV'T. OF ACCESS ROAD LEADING TO FRANCISCO B. REYE S AIRPORT (BRGY. SAN NICOLAS TO BRGY. DECALACHAO), STA. 16+368.00 TO STA. 2 2+129.00, CORON, PALAWAN
- Contractor: TIERRA DE FERRAND REALTY & DEVELOPMENT CORPORATION (41266) / ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION) (15199)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-06-18
- Fund source: Regular Infra - GAA 2019 CSSP
- Contract price: ₱144,392,976.00
- Contract status: Completed Report
- WIDENING OF PUERTO PRINCESA NORTH ROAD (PPNR), KO141+100.0 0 - KO142+472.00, ROXAS, PALAWAN
- Contractor: TCSC CORP. (15453)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-05-13
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱101,182,384.00
- Contract status: Completed Report
- WIDENING OF MALATGAO BRIDGE, KO082+340.00 - KO082+820.00, NARRA, PALAWAN
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651) / ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION) (15199)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2021-06-17
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱144,413,808.00
- Contract status: Completed Report
- CONSTRUCTION OF CRUISE PORT AND FACILITIES - PACKAGE A, PT O. PRINCESA CITY, PALAWAN
- Contractor: EQUI-PARCO CONSTRUCTION COMPANY (14332)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-08-19
- Fund source: Regular Infra - GAA 2019 LP
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- CONSTRUCTION OF CRUISE PORT AND FACILITIES - PACKAGE B, PU ERTO PRINCESA CITY, PALAWAN
- Contractor: EQUI-PARCO CONSTRUCTION COMPANY (14332)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-08-19
- Fund source: Regular Infra - GAA 2019 LP
- Contract price: ₱193,000,000.00
- Contract status: Completed Report
- CONST./IMPROVEMENT OF SAN JOSE CIRCUMFERENTIAL ROAD, STA. 8+532.00 - STA. 8+840.00, SAN JOSE, ROMBLON
- Contractor: MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. (5733)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2021-12-29
- Fund source: Regular Infra - GAA 2019 CSSP
- Contract price: ₱105,950,056.00
- Contract status: Completed Report
- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LA NDSLIDE ALONG TABLAS CIRCUMFERENTIAL ROAD, KO034+185.00 - KO034+568.00, ROM BLON
- Contractor: LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) (22465)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-12-20
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱148,944,560.00
- Contract status: Completed Report
- CONSTRUCTION OF MISSING LINKS/NEW ROADS OF ODIONGA EAST WE ST ROAD, STA. 8+940 TO STA. 9+670, ODIONGAN, ROMBLON
- Contractor: LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) (22465)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2021-05-11
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱107,835,000.00
- Contract status: Completed Report
- RETROFITTING/STRENTHENING OF LUMINTAO BRIDGE ALONG MINDOR O WEST COASTAL ROAD, MINDORO OCCIDENTAL
- Contractor: KEJAMARENIK CONSTRUCTION & CONSTRUCTION SUPPLIES (33742) / KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2021-02-19
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱134,995,456.00
- Contract status: Completed Report
- CONSTRUCTION OF CONCRETE PARALLEL BRIDGE - PAGBAHAN BRID GE ALONG MINDORO WEST COASTAL ROAD, MINDORO OCCIDENTAL
- Contractor: PLERM CONSTRUCTION AND DEVELOPMENT CORPORATION (33288)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-09-24
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱154,272,096.00
- Contract status: Completed Report
- ROAD WIDENING OF F.B. REYES (BUSUANGA-CORON) ROAD, KO014+ 951.50-KO015+200.00, KO015+300-KO016+029.00, KO017+843.00-KO020+855.00, COR ON, PALAWAN
- Contractor: KATHA BUILDERS & SUPPLIES INC. (34651)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2020-12-20
- Fund source: Regular Infra - GAA 2019 OO-1
- Contract price: ₱144,555,584.00
- Contract status: Completed Report
- CONSTRUCTION OF BALABAC MILITARY RUNWAY, STA. 1+350.00 - STA. 2+658.00, BALABAC, PALAWAN
- Contractor: ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION) (15199)
- Implementing Agency: Region IV-B - Region IV-B
- Region: Region IV-B
- Contract effectivity:
- Contract expiry: 2022-04-03
- Fund source: Regular Infra - GAA 2019 CSSP
- Contract price: ₱48,244,628.00
- Contract status: Completed Report