Infrastructure Projects in Region VII — Region VII - Bohol 2nd District Engineering Office, 2020
This page lists public infrastructure projects implemented by Region VII - Bohol 2nd District Engineering Office in Region VII during 2020. All data are sourced from the Department of Public Works and Highways (DPWH) official database (as of 9/30/2025): https://www.dpwh.gov.ph/dpwh/projects/infrastructure
This information is shared to promote transparency and public awareness. We encourage visitors to validate project details using the official DPWH source. In case of discrepancies, please refer to the original records published by the DPWH.
| Contractor | Projects | Total Price |
|---|---|---|
| LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524) | 7 | ₱169,926,418.50 |
| CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043) | 8 | ₱160,371,268.00 |
| YS CONSTRUCTION (11928) | 6 | ₱124,403,147.00 |
| RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901) | 19 | ₱91,686,155.06 |
| INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764) | 13 | ₱56,591,700.50 |
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSE T PRESERVATION -PREVENTIVE MAINTENANCE- SECONDARY ROADS: TAGBILARAN NORTH R D (TAGBILARAN-JETAFE SECT.) K0087+442-K0087+574, K0087+721 -K0087+918, K008 9+000- K0089+509, K0090+400 - K0090+1010,K0096+2
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-03
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱10,220,269.00
- Contract status: Completed Report
- OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASS ET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE -SECONDARY ROAD- TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)- (S00104BH) K0115+520-K0116+000, K0116+0 00-K0116+005, (S00146BH) CHAINAGE 0+028-0+154, I
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-14
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱7,867,352.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSE T PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- SECONDARY ROADS - LOAY INTERIOR RD- K0122+155- K0122+604, K0139+582 - K0139+765, TRINIDAD AND SAN MIGUEL. BOHOL
- Contractor: CEVIC CONSTRUCTION & DEVELOPMENT CORP. (18015)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-27
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱23,056,436.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSE T PRESERVATION PROGRAM- REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- SECONDARY ROADS- TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)- K0112+116 - K0112+226, TALIBON, BOHOL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-03-02
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱4,509,097.50
- Contract status: Completed Report
- OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGE D PAVED ROADS- TERTIARY ROADS: SAGBAYAN- DANAO RD- K0086+123 - K0086+201, I NABANGA, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-03
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱2,967,508.50
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM- REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED P AVED ROADS - TERTIARY ROADS: SAGBAYAN-DANAO RD - K0087+158 - K0088+000, INA BANGA, BOHOL
- Contractor: YS CONSTRUCTION (11928)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-26
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱30,841,220.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSE T PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WI TH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SLOPE COLLAPSE AND LANDSLIDE - TERTI ARY ROADS, SAGBAYAN- DANAO RD K0077+(-050) - K007
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-08
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱1,912,806.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETW ORK DEVELOPMENT PROGRAM- ROAD WIDENING - SECONDARY ROADS - TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)K0059+199 - K0060+262, K0060+497 - K0060+747, C LARIN, BOHOL
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-06-27
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱36,500,000.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETW ORK DEVELOPMENT PROGRAM-ROAD WIDENING-TERTIARY ROADS-UBAY BY-PASS RD- K0137 +(607)-K0137+(-447), K0137+095-K0137+351, UBAY, BOHOL
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-11
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱15,691,389.00
- Contract status: Completed Report
- OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETW ORK DEVELOPMENT PROGRAM- OFF-CARRIAGEWAY IMPROVEMENT- SECONDARY ROADS- JCT. (LIR) CARMEN-SAGBAYAN-BACANI RD.- K0184+000-K0187+000, CLARIN, BOHOL
- Contractor: YS CONSTRUCTION (11928)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-23
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱28,517,888.00
- Contract status: Completed Report
- OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM -NETW ORK DEVELOPMENT PROGRAM- OFF-CARRIAGEWAY IMPROVEMENT- SECONDARY ROADS -LOAY INTERIOR RD - K0126+064 - K0127+491; K0128+392 -K0129+500; K0130+840 - K01 31+101 AND K0137+350 - K0137+958, TRINIDAD AND
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-07-01
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱38,250,000.00
- Contract status: Completed Report
- NETWORK DEVELOPMENT OFF-CARRIAGEWAY IMPROVEMENT: TAGBILA RAN EAST RD (TAGBILARAN-JAGNA)- K0140+226 - K0141+800; K0144+076 - K0145+00 0, K0145+512 - K0146+000, UBAY, BOHOL
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-06-24
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱33,779,408.00
- Contract status: Completed Report
- OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM -NETW ORK DEVELOPMENT PROGRAM- OFF-CARRIAGEWAY IMPROVEMENT -SECONDARY ROADS -TAGB ILARAN NORTH ROAD (TAGBILARAN-JETAFE SECT) -K0062+340 -K0062+436, K0067+616 - K0070+900, CLARIN AND INABANGA, BOHOL
- Contractor: YS CONSTRUCTION (11928)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-23
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱28,509,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROADS LEADING TO SEAPORT- ACCESS ROAD LEADING TO TALIBON PORT VIA SAN JOSE-BRGY. SAN FRANCISCO- REVILLES ST.,BRGY. POBLACION , TALI BON, BOHOL
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-30
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱18,620,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO TAPAL WHARF VIA ROAD TO PALAYAN NG BAYAN - BRGYS. IMELDA AND BENLIW, UBAY, BOHOL
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-25
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱9,408,161.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS- ACCESS ROAD LEADING TO UBAY P ORT VIA RECLAMATION AREA, UBAY, BOHOL
- Contractor: CEVIC CONSTRUCTION & DEVELOPMENT CORP. (18015)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-03-22
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱18,807,852.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: ACCESS R OAD LEADING TO BARANGAY TAPAL WHITE BEACH, BRGY. TAPAL, UBAY, BOHOL< /li>
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-25
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱8,673,467.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS- ACCESS ROADS LEADING TO TONTUNAN HIGHLAND, BRGY. TONTUNAN, CLARIN, BOHOL
- Contractor: YS CONSTRUCTION (11928)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-16
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱14,236,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS- CANTOYO C BRGY. ROAD LEADING TO BINALIW FALLS, BRGY. CANTOYOC, CLARIN, BOHOL
- Contractor: YS CONSTRUCTION (11928)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-04
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,839,639.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS DANAO-SA GBAYAN ROAD JCT. TO STO. NI C3 91O TO MAGTANGTANG BARANGAY ROAD LEADING TO DANAO ADVENTURE PARK, DANAO, BOHOL
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-25
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱9,309,178.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: AT HINL AYAGAN ILAYA-BANLASAN-SAN ISIDRO ROAD LEADING TO KAWASAN FALLS, BRGY.HINLAY AGAN ILAYA, TRINIDAD, BOHOL
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-21
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,526,525.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/ IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS- JCT. TE R MABUHAY-GABI-BAYONGAN- CAMANAGA ROAD LEADING TO BAYONGAN DAM, UBAY, BOHOL
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-08-03
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱22,040,210.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IM PROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS AT M. CAB IGUHAN-KINAN-OAN-KAUSWAGAN-DIIS(TRINIDAD)- CANDIIS, SAN CARLOS-MAGTANGTANG, DANAO LEADING TO DANAO ADVENTURE PARK, BRGY. KAU
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-25
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱9,408,366.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS: POBLACION TO SITIO CATOOGAN CANDUNGAO BRGY. ROAD LEADING TO CANDUNGAO PEAK TOURISM S ITE, BRGY. POBLACION, SAN ISIDRO, BOHOL
- Contractor: WYNN CONSTRUCTION AND DEVELOPMENT CORPORATION(FORMERLY: WYNN CONSTRUCTION) (19358)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-23
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱9,310,000.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM -CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS -SAN MI GUEL-BAYONGAN-BULILIS-MABUHAY(UBAY) ROAD LEADING TO DANAO ADVENTURE PARK, U BAY, BOHOL
- Contractor: CEBU 7H TECHNOCHEM INDUSTRIES, INC. (31578)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-08-22
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱28,156,846.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS: TAMING BA RANGAY ROAD LEADING TO GRAND CANYON VIEW OF DANAO ADVENTURE PARK, BRGY. TAM ING, DANAO, BOHOL
- Contractor: CEBU 7H TECHNOCHEM INDUSTRIES, INC. (31578)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-23
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱9,312,411.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS- TAMING- VILLA ANUNCIADO ROAD LEADING TO HIGHLAND TOURISM, BRGY. TAMING, DANAO, BOH OL
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-08-28
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱27,926,274.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO TRADES,INDUSTRIES AND ECONOMIC ZONES: CA TIGBIAN-CLARIN VIA BOGTONGBOD ROAD (CLARIN SIDE) CONNECTING CORTES-BALILIHA N-CATIGBIAN-MACAAS ROAD AND CLARIN-SAGBAYAN-CARME
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-25
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,565,600.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/I MPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - CANTUBOD- DAGOHOY- CAUSWAGAN BARANGAY ROAD CONNECTING PALM OIL PLANTATION TO DANAO- GETAFE ROAD, DANAO, BOHOL
- Contractor: LEDA CONSTRUCTION INCORPORATED (12229)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-04
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱6,261,637.50
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO TRADES,INDUSTRIES & ECONOMIC ZONES: JCT. (LIR) MAHAYAG(SAN MIGUEL)- DANAO ROAD IN SUPPORT OF THE AGRIBUSINESS I NDUSTRY, SAN MIGUEL, BOHOL
- Contractor: LEDA CONSTRUCTION INCORPORATED (12229)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-20
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,026,141.50
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES- LAPACAN SUR (BUGTONG-LUBI) INABANGA- MAGTANGTANG (DANAO)ROAD, DANAO, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-25
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,601,756.50
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IM PROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - LUBANG- NUEVA MONTANA- BUNGA ROAD CONNECTING TAGBILARAN NORTH ROAD TO DAN AO-GETAFE ROAD IN SUPPORT OF GIFTS AND HOUSEWARES
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-19
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,447,789.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: M ABUHAY(UBAY)- BULILIS-BAYONGAN SAN MIGUEL ROAD CONNECTING LOAY INTERIOR ROA D AND TAGBILARAN EAST ROAD IN SUPPORT TO FURNITUR
- Contractor: WYNN CONSTRUCTION AND DEVELOPMENT CORPORATION(FORMERLY: WYNN CONSTRUCTION) (19358)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-08-22
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱22,902,600.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IM PROVEMENT OF ACCESS ROAD LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: MAGTANGTANG-CARBON-CABATUAN BARANGAY ROAD CONNECTING CABATUAN LOOMWEAVING C ENTER TO SAGBAYAN-DANAO ROAD IN SUPPORT OF GIFTS
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-16
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,447,550.50
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/IMP ROVEMENT OF ACCESS ROAD LEADING TO TRADES INDUSTRIES AND ECONOMIC ZONES: PO BLACION- MASONOY-CANDUNGAO (CENTRO) ROAD CONNECTING TO TAGBILARAN NORTH ROA D AND ANTEQUERA, SAN ISIDRO-LIBERTAD ROAD IN THE
- Contractor: S AND CU CONSTRUCTION (13128)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-09
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱9,358,500.00
- Contract status: Completed Report
- CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IM PROVEMENTOF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES- TALIBON CAUSEWAY BYPASS- FROM POBLACION-VIA BARANGAY SAN FRANCISCO- BARANGA Y SAN JOSE ROAD CONNECTING TAGBILARAN NORTH ROAD
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-21
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱7,599,962.50
- Contract status: Completed Report
- CONSTRUCTION OF BOHOL 2ND DISTRICT ENGINEERING OFFICE FA CILITIES, BOOD, UBAY, BOHOL
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-26
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱9,701,898.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SAN MIGUEL, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-06-13
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱3,331,153.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD BRGY. BOGO, GETAFE, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-19
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,017,794.50
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, BRGY. LONOY TO BRGY. CAINSICAN, IN ABANGA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-03-31
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱1,588,192.62
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, BRGY. NABUAD AND BRGY. DAIT, INABA NGA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-03-31
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱1,468,974.88
- Contract status: Completed Report
- CONSTRUCTION OF ROAD, BRGY. POBLACION, SAGBAYAN, BOHOL
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-04-14
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱3,723,580.50
- Contract status: Completed Report
- IMPROVEMENT OF BARANGAY CASATE-TUBOG-BUGANG ROAD, SECTIO N 3, UBAY, BOHOL
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-19
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱42,289,856.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. ACHILA, U BAY, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱837,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. ANONANG, INABANGA, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱801,145.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BACANI, CLARIN, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱814,600.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BAGACAY, TALIBON, BOHOL
- Contractor: J.F. ESTAPIA CONSTRUCTION (40112)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-25
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱760,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BAGO, BU ENAVISTA, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BALINTAWA K, TALIBON, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BAUD, C.P . GARCIA, BOHOL
- Contractor: R.F. VARQUEZ CONSTRUCTION (24302)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱805,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BONGBONG, UBAY, BOHOL
- Contractor: J.F. ESTAPIA CONSTRUCTION (40112)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱765,140.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BONOTBON OT, BUENAVISTA, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱839,878.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BUENAVIS TA, UBAY, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱825,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BUGANG, SAN MIGUEL, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱828,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BURGOS, T ALIBON, BOHOL
- Contractor: GERSON CONSTRUCTION AND HARDWARE SUPPLY (44434)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱741,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BUTAN, C .P. GARCIA, BOHOL
- Contractor: C. JANSEN CONSTRUCTION AND GENERAL MERCHANDISE (46056)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-08-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,200.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. BUYOG, GE TAFE, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-15
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱970,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CABANGAH AN, SAN MIGUEL, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-09
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱839,795.62
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CABOY, C LARIN, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱814,900.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CAGTING, UBAY, BOHOL
- Contractor: JECK CONSTRUCTION (24189)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱985,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. CALUASAN, DAGOHOY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱819,970.56
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. CAMBANGAY NORTE, SAN MIGUEL, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱764,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. CAMBUS-OC OCC., BUENAVISTA, BOHOL
- Contractor: JECK CONSTRUCTION (24189)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. CAMPAO OR IENTAL, GETAFE, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱970,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CANTOYOK , CLARIN, BOHOL
- Contractor: R.F. VARQUEZ CONSTRUCTION (24302)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱830,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. CAPAYAS, SAN MIGUEL, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱837,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CORAZON, SAN MIGUEL, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-09
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱787,935.81
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CUYA, UB AY, BOHOL
- Contractor: JECK CONSTRUCTION (24189)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. FATIMA, INABANGA, BOHOL
- Contractor: MAI CONSTRUCTION & SUPPLY (30839)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱995,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. GOV. BOYL ES, UBAY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱970,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. HANDUMON , GETAFE, BOHOL
- Contractor: C. JANSEN CONSTRUCTION AND GENERAL MERCHANDISE (46056)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱900,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. HUNAN, BU ENAVISTA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. KATIPUNA N, SAGBAYAN, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱970,690.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. LA ESPERA NZA, DAGOHOY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱985,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LANGTAD, SAGBAYAN, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱929,650.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. LAPINIG, C.P. GARCIA, BOHOL
- Contractor: C. JANSEN CONSTRUCTION AND GENERAL MERCHANDISE (46056)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱994,440.62
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LIBERTAD NORTE, SAGBAYAN, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-09
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱908,360.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LIBERTAD SUR, SAGBAYAN, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-09
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱908,360.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LIBERTY, BIEN UNIDO, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱822,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LONOY RO MA, INABANGA, BOHOL
- Contractor: MAI CONSTRUCTION & SUPPLY (30839)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱969,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LOS ANGE LES, UBAY, BOHOL
- Contractor: J.F. ESTAPIA CONSTRUCTION (40112)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱765,032.81
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LUTAO, I NABANGA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱749,379.25
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. MAGSAYSAY , TALIBON, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱900,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. MARIA RO SARIO, INABANGA, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱815,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. ONDOL, I NABANGA, BOHOL
- Contractor: MAI CONSTRUCTION & SUPPLY (30839)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱792,490.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. PAG-ASA, UBAY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱897,504.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. PANGPANG, UBAY, BOHOL
- Contractor: DTV CONSTRUCTION AND SUPPLY (38257)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-15
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱889,998.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. POBLACION , C.P. GARCIA, BOHOL
- Contractor: R.F. VARQUEZ CONSTRUCTION (24302)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱820,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. PUERTO SA N PEDRO,BIEN UNIDO, BOHOL
- Contractor: J.F. ESTAPIA CONSTRUCTION (40112)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱765,040.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. RUFO HIL LS, BUENAVISTA, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱820,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SAN AGUST IN, TALIBON, BOHOL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-16
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱883,300.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. SAN ANTO NIO, SAGBAYAN, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-09
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱901,580.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SAN CARLO S, TALIBON, BOHOL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-15
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱893,200.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. SAN ISID RO, SAGBAYAN, BOHOL
- Contractor: JJF BUILDERS AND SUPPLY (37015)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱969,971.38
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. SAN ISID RO, UBAY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱880,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. SAN JOSE , GETAFE, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SAN MIGUE L, DAGOHOY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱988,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SAN VICEN TE, C.P. GARCIA, BOHOL
- Contractor: R.F. VARQUEZ CONSTRUCTION (24302)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-08
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱820,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SAN VICEN TE, DAGOHOY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱989,900.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SAN VICEN TE, UBAY, BOHOL
- Contractor: JECK CONSTRUCTION (24189)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. SIKATUNA, TALIBON, BOHOL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-15
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. STO.NI C3 91O, INABANGA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱809,899.19
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. STO NI C3 91O, SAN MIGUEL, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱837,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. STO. ROS ARIO, INABANGA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱827,970.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. SUA, INA BANGA, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱860,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. TUBOG, UB AY, BOHOL
- Contractor: MAI CONSTRUCTION & SUPPLY (30839)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱830,015.75
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. TUBORAN, BIEN UNIDO, BOHOL
- Contractor: C. JANSEN CONSTRUCTION AND GENERAL MERCHANDISE (46056)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱809,956.62
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING BRGY. TUGNAO, C .P. GARCIA, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱990,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. TUNGOD, INABANGA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-22
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱827,934.31
- Contract status: Completed Report
- OO1: ENSURE SAFE AND NATIONAL ROAD SYSTEM- ASSET PRESERV ATION PROGRAM- REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROAD- TAGBILARAN NORTH RD (TAGBILAR AN-JETAFE SECT) K0102+065.00 - K0102+167.00, GETA
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-17
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱2,993,175.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- OFF- CARRIAGEWAY IMPROVEMENT- SECONDARY ROADS- TAGBILARAN NORTH RD (TAGBILARAN-J ETAFE SECT) -K0085+626 - K0086+543, K0107+766 - K0108+795 & K0115+016 - K0115+518, BUENAVISTA AND TALIBON, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-05-13
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱19,414,656.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. HINGOTAN AN WEST, BIEN UNIDO, BOHOL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-25
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱995,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. TILMOBO, C.P. GARCIA, BOHOL
- Contractor: AMAZING FIND BUILDERS CORPORATION (FORMERLY: SKILLED CONTRACTORS & LABORERS EMPOWERMENT COOPERATIVE) (32932)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-05-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱921,500.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, INABANGA, BOHOL
- Contractor: JJF BUILDERS AND SUPPLY (37015)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-07-03
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱14,839,321.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. NAHAWAN, CLARIN, BOHOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-28
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱891,000.00
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING (BRGY.HEALTH ST ATION), BRGY. CONCEPCION, DANAO, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-28
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱787,500.00
- Contract status: Completed Report
- CONSTRUCTION OF MUNICIPAL PLAZA IN BRGY. POBLACION, PRES . CARLOS P. GARCIA, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-13
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,900,500.00
- Contract status: Completed Report
- CONSTRUCTION OF DANAO MULTI-PURPOSE BUILDING, DANAO, BOH OL
- Contractor: C. JANSEN CONSTRUCTION AND GENERAL MERCHANDISE (46056)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-21
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱1,960,000.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BUENAVISTA, BO HOL
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-17
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱1,920,600.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE FACILITY (SPORTS & EX HIBITION CENTER), BRGY. POBLACION, TALIBON, BOHOL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-07-06
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱9,855,450.00
- Contract status: Completed Report
- CONSTRUCTION OF PUBLIC MARKET BUILDING FOR THE BIEN UNID O, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-01
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,900,141.00
- Contract status: Completed Report
- COMPLETION OF MULTI-PURPOSE BUILDING AT BRGY. POBLACION, TALIBON, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-14
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱8,043,612.00
- Contract status: Completed Report
- CONSTRUCTION OF DAGOHOY MUNICIPAL GYMNASIUM, DAGOHOY BOH OL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-07-03
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱14,775,750.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS & EXH IBITION CENTER), TALIBON, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-06-23
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱19,695,000.00
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. CAGAWITAN, DAGOHOY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,895,000.00
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. VILLA AURORA, DAGOHOY, BOHOL
- Contractor: C. JANSEN CONSTRUCTION AND GENERAL MERCHANDISE (46056)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,886,217.00
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. EASTERN CABUL-AN, BUENAVISTA, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,894,061.50
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. PITOGO, CARLOS P. GARCIA (DAO) BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-20
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,900,823.00
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. POBLACION, SAGBAYAN, BOHOL
- Contractor: SLP CONSTRUCTION (35992)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-11
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,846,080.00
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. SAN JOSE, TALIBON, BOHOL
- Contractor: J.F. ESTAPIA CONSTRUCTION (40112)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-05-12
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,089,437.00
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, CAMBANSAG NATIONAL HIGH SCHOOL, SAN ISIDRO, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-12
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱2,902,038.25
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, CANDUNGAO NATIONAL HIGH SCHOOL, SAN ISIDRO, BOHOL
- Contractor: EDTAHA BUILDERS INC. ( FORMERLY: JSP BUILDERS & GENERAL MERCHANDISE) (37249)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱1,900,230.12
- Contract status: Completed Report
- REHABILITATION OF MULTI-PURPOSE BUILDING ( MULTI-PURPOSE HALL) BRGY. BOOD, UBAY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-17
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱2,910,600.00
- Contract status: Completed Report
- CONSTRUCTION/RENOVATION OF DANAO MUNICIPAL BUILDING, DAN AO, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-20
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱2,950,976.50
- Contract status: Completed Report
- CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPO SE BUILDING, BRGY. POBLACION, SAN MIGUEL, BOHOL
- Contractor: CLAVITE CONSTRUCTION AND SUPPLY (40502)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-02-15
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,888,502.50
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, UBAY, BOHOL
- Contractor: WBV CONSTRUCTION (42790)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-07-04
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱3,797,568.75
- Contract status: Completed Report
- CONCRETING OF BRGY. ROAD SITIO KABULAKAN, LOMANGOG, UBAY , BOHOL
- Contractor: FUENTABUILT CONSTRUCTION CORP. (36098)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-01
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱11,408,586.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), SAN PASCUAL, UBAY, BOHOL
- Contractor: MAI CONSTRUCTION & SUPPLY (30839)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-12
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,802,000.00
- Contract status: Completed Report
- CONSTRUCTION/CONCRETING OF ROAD APPROACHES, BRGY. BIABAS , UBAY, BOHOL
- Contractor: J.F. ESTAPIA CONSTRUCTION (40112)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-06
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱11,193,465.00
- Contract status: Completed Report
- 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETW ORK DEVELOPMENT PROGRAM OFF-CARRIAGEWAY IMPROVEMENT- TERTIARY ROADS- SAGBAY AN-DANAO RD- K0086+201-K0087+019, K0090+000-K0090+181, K0090+310-K0091+143, SAGBAYAN AND DANAO, BOHOL
- Contractor: YS CONSTRUCTION (11928)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-05-05
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱14,459,400.00
- Contract status: Completed Report
- CONSTRUCTION OF LOCAL ROAD IN BRGY. TIPOLO, UBAY, BOHOL< /span>
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-11-30
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱2,851,000.00
- Contract status: Completed Report
- CONSTRUCTION/CONCRETING OF ROAD, BRGY. POBLACION-BRGY.TU MOC, SAN MIGUEL, BOHOL
- Contractor: CCMALUENDA CONSTRUCTION INC. (FORMERLY:C.C.M. CONSTRUCTION) (11043)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-06-09
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱33,594,096.00
- Contract status: Completed Report
- CONCRETING OF BONOT-BONOT ROAD, BRGY. BONOT-BONOT, BUENA VISTA, BOHOL
- Contractor: BNYU DEVELOPMENT CORPORATION (FORMERLY:BNYU ENTERPRISES & CONSTRUCTION) (27725)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-06-02
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱28,364,568.00
- Contract status: Completed Report
- REHABILITATION OF THE ROAD AT BRGY. BONBON, CLARIN, BOHO L
- Contractor: M.M. SUAREZ CONSTRUCTION & SUPPLY (41341)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-11-29
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,835,080.50
- Contract status: Completed Report
- CONSTRUCTION OF CAPAYAS BRIDGE, BRGY. CAPAYAS, SAN MIGUE L, BOHOL
- Contractor: LABB CONSTRUCTION DEVELOPMENT INC. (FORMERLY: LABB CONSTRUCTION) (13524)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-06-15
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱18,989,972.00
- Contract status: Completed Report
- CONSTRUCTION/REHABILITATION OF JCT. (LIR) SAN MIGUEL- BA YONGAN- BULILIS- MABUHAY, UBAY ROAD, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-03-03
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱19,601,708.00
- Contract status: Completed Report
- CONSTRUCTION OF LEVEL II WATER SUPPLY SYSTEM , UBAY, BOH OL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-03-29
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱8,731,468.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), GETAFE, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-03-17
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱3,993,400.00
- Contract status: Completed Report
- CONSTRUCTION OF MULTI-PURPOSE SPORTS FACILITY IN BRGY. P OBLACION, TALIBON, BOHOL
- Contractor: 3N CONSTRUCTION & SUPPLY (37872)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-05-24
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱7,933,173.00
- Contract status: Completed Report
- CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, BUENAVIST A, BOHOL
- Contractor: INABANGA DRILLING, CONSTRUCTION, STEEL FABRICATION, AND GEN. MDSE. (35764)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-04-04
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱17,110,800.00
- Contract status: Completed Report
- CONSTRUCTION/COMPLETION OF WATER SYSTEM (LEVEL III), BRG Y. LOMANGOG, UBAY, BOHOL
- Contractor: RUDHIL CONSTRUCTION & ENTERPRISES, INC.(FORMERLY R (22901)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-01-17
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱4,802,000.00
- Contract status: Completed Report
- CONSTRUCTION & IMPROVEMENT OF THE MUNICIPAL HALL OF SAN MIGUEL, BOHOL
- Contractor: SOMBRIO CONSTRUCTION AND SUPPLY (39384)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-07-03
- Fund source: Regular Infra - GAA 2020 LP
- Contract price: ₱9,700,000.00
- Contract status: Completed Report
- CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS-18 UNIT S), BOHOL 2ND DISTRICT
- Contractor: MAI CONSTRUCTION & SUPPLY (30839)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2020-12-26
- Fund source: Regular Infra - GAA 2020 CSSP
- Contract price: ₱2,952,548.75
- Contract status: Completed Report
- ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIO NAL ROAD SYSTEM- NETWORK DEVELOPMENT- ROAD WIDENING- SECONDARY ROADS- TAGBI LARAN NORTH RD (TAGBILARAN-JETAFE SECT) K0113+070 - K0113+531, TALIBON, BOH OL
- Contractor: PRIMABUILD CONSTRUCTION INC. (39211)
- Implementing Agency: Region VII - Bohol 2nd District Engineering Office
- Region: Region VII
- Contract effectivity:
- Contract expiry: 2021-05-05
- Fund source: Regular Infra - GAA 2020 OO-1
- Contract price: ₱12,723,415.00
- Contract status: Completed Report